Resolved that the Assistant Executive Director (Performance and Business Management) be authorised to - (i) enter into respective 1 year service based contracts with Enterprise-Liverpool for the Neighbourhood Package and Glendale for the Parks Package with an option for the City Council to extend the arrangement for up to 12 years subject to conclusion of the joint venture agreements. Reviews of the contract arrangements taking place every 4 years; (ii) jointly continue the current negotiation phase with both of the above named companies and to formalise the long term joint venture/partnership arrangements within the next 6 months; (iii) continue the current consultation arrangements to TUPE all staff involved in the scope of the services outlined in this report for the delivery of Year 1 base services in Parks and Neighbourhoods; (iv) continue the TUPE consultation and roll out for staff working in service streams that are the subject of further negotiation during the next period; (v) to provide an information report back to the Executive Board of the detailed arrangements resulting from the negotiations for each of the contract packages and the associated details of the contract/partnership arrangements within a 6 month period; (vi) for the City Council to underwrite associated advanced mobilisation costs as detailed in the body of this Report to enable the respective packages to commence service delivery on the 31 March 2006; and (vii) authorise further short term extensions to the existing contracts in the event of the failure to finalise contracts with respective providers to enable commencement of the contracts on the 31 March 2006.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
To advise and seek the approval of the Executive Board for the proposed contract arrangements regarding the appointment of Preferred Bidders to deliver Grounds Maintenance Services to Parks and Neighbourhoods.
Background
The Executive Report entitled “Grounds Procurement Approval of Preferred Bidders” (LS&C/12) authorised Officers to enter negotiations with Enterprise- Liverpool for the delivery of grounds services for the Neighbourhood Package, and with Glendale for the Parks Package.
Negotiations have commenced and related consultation exercises are under way with the unions, staff and other stakeholders.
The negotiations commenced by assessing critical issues relating to the change in service delivery arrangements as noted below.
• Timescale for mobilisation • TUPE implications and numbers • Structure of Contract/Partnership Models • Finance • Detail Budget Costs of service delivery in Year 1 • The City’s immediate service delivery requirements • Performance Management Framework Negotiations have progressed with the two Preferred Bidders. Arrangements regarding the delivery of Grounds Maintenance Services through the existing contracts have been put in place until March 31 in line with previous resolutions. These arrangements are operating within the terms of contract extensions and the cost is based on the rates contained in original CCT contracts. Costs for the delivery of these services will be contained within the 2005/2006 revenue budget.
3.0Negotiation Process
The City’s negotiating Team is lead by Assistant Executive Director of Resources (Treasury and Risk Management) and has representation from the following areas.
• Contracts and Partnerships • Parks and Environment • Outdoor Leisure • Finance • Human Resources • Legal Services
The negotiation process covers the matters listed below.. • Agreeing appropriate contact/partnership arrangements • Establishing service delivery costs Year 1 • Determining all financial arrangements between the City and the future providers/partners • Formalising governance, management and client arrangements. • Agreement of payment mechanisms. • Agreement of the performance management framework and performance standards. • Finalising the Business Plan for Year 1 and establishing appropriate milestones relating to all aspects of the service. • Finalising the initial scope of services to be incorporated in to the new arrangements. • Agreeing the timescales for the different service streams to be included. • Details of all TUPE arrangements and organising the associated consultation arrangements across all parties. • Agreement of Method Statements for all aspects of the base service delivery for Year1.
It has been established that in order to commence the new arrangements on the 31 March 2006 the scope of services that can be included at the outset is the current base service plus some closely related functions currently carried out by LCC staff. The scope of services for each package are listed below. Neighbourhood Package:
1. Cyclic works to verges, amenity open spaces and related housing and social services spaces. 2. Arboricultural works and associated client staff 3. Associated client staff to support Neighbourhood Management activities. 4. Outline neighbourhood improvement program
Parks Package:
1. Cyclic works to all areas 2. Cemeteries and crematoria ground maintenance services 3. Park and Leisure Attendants 4. Arboricultural works 5. Gardening staff 6. Apprentices 7. Outline Parks improvement program
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.