Salford City Council
Procurement Board, Monday 23 March 2026 at 2.00pm

Approval to go out to tender/ competition for Chapel Street/ Trinity Way Junction Procurement (Opu Anwar)

Approved Committee 1 paper

AI summarySalford City Mayor approves competitive tender for Chapel Street/Trinity Way junction works, estimated at £1.5 million, with delivery targeted for summer 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedVia Bolton Highways Framework, Lot 1 mini-competition
Money£1.5 million estimatedPlus £726,249 Section 106 from Gore Street
What happens nextDecision in force 31 March 2026At 4.00 p.m. unless called in
Who it affectsOrdsall, Blackfriars and Trinity wardsChapel Street/Trinity Way junction area

What was decided

The City Mayor accepted the Procurement Board recommendation to run a competitive tender for the Chapel Street/Trinity Way junction CRSTS works through the Bolton Highways Framework. Report P1

Authority was delegated to the Deputy Chief Executive (Executive Director Place), in consultation with the Lead Member for Planning, Transport and Sustainable Development, to approve submission of a business case to Transport for Greater Manchester. Report P2, P29

Why

The junction currently has no controlled crossings on the Chapel Street arms and a deteriorating carriageway surface, creating safety and accessibility issues for people moving between Chapel Street, Trinity, Islington and the city centre. Report P11

An interim scheme is required because the earlier CYCLOPS arrangement cannot progress now due to unresolved traffic impact concerns and the need to align with the emerging City Centre Movement Strategy. Report P12

Salford has Programme Entry approval and must contractually commit the scheme by March 2027, with co-ordination needed with a Salford Active Travel scheme and a major Manchester Council scheme planned for early 2027. Report P14, P36, P50

What happens next

Run a mini-competition under Lot 1 of the Bolton Highways Framework, which has 5 approved contractors, to obtain a tendered price needed for the business case. Report P17, P52

Submit the Strategic Outline Business Case to Transport for Greater Manchester, with delivery of the works targeted for summer 2026. Report P29, P50

Consider a separate procurement for a complementary package of works to strengthen parallel cycle routes, as the interim scheme will not deliver the full active travel benefits of the original proposal. Report P15, P28

The money

  • £1.5 million Estimated tender cost for the junction works (not including fees, risk, contingencies) Report P27, P48
  • £726,249 Section 106 funding from the Gore Street development, earmarked for pedestrian improvements at the junction Report P26, P49
  • £0.726m Section 106 funding available to support improvements at the junction Report P49

Options considered

  • Chosen: Run a mini-competition under Lot 1 of the Bolton Highways Framework. Provides access to experienced contractors already appointed through a compliant procurement process; compliant with Council standing orders and PCRs Report P17, P41, P52
  • Rejected: Direct award of works

Implications

  • Financial: Estimated tender costs of £1.5 million fall within the CRSTS budget; remainder to be used for complementary cycle route improvements. Risk of CRSTS funding clawback if not contractually committed by March 2027. Report P48, P50
  • Legal: The Council must comply with the Procurement Act 2023 and its own Contractual Standing Orders; a framework arrangement is to be used. Report P40, P41
  • Equalities: An Equality Impact Assessment has been carried out. Report P34
  • Climate: Climate change implications are to be supplied at contract award stage. Report P54
  • Risk: Risk assessed as High: contractual commitment required by March 2027 and works must be co-ordinated with other local projects to avoid severe highway network congestion. Report P36, P50
  • Other: The interim scheme will not deliver the full active travel benefits of the original MCF proposal; a complementary package of cycle route works is being considered under a separate procurement route. Report P15, P22, P47

Who and where

  • Residents and road users in the Ordsall, Blackfriars and Trinity wards Report P58
  • People using Salford Central Railway Station and the key bus corridor on Chapel Street Report P10
  • Pedestrians and cyclists using the wider walking and cycling network around the city centre Report P10, P11
  • Five contractors listed under Lot 1 of the Bolton Highways Framework Report P52

Timeline

  • 15th February 2022: Strategic Director Place report to Lead Member (Part 2) Report P5
  • 9th July 2025: Strategic Director Place report to Lead Member (Part 2) Report P6
  • 2024: Programme entry granted for the CRSTS scheme Report P25, P48
  • 03/03/26: Legal advice obtained from Rebecca Maddison
  • 03/03/26: Procurement advice obtained from Heather Stanton
  • 05/03/26: Financial advice obtained from Grace Rogerson
  • 23 March 2026: Decision signed by City Mayor
  • 24 March 2026: Decision published
  • 31 March 2026: Decision comes into force at 4.00 p.m. unless called in
  • Summer 2026: Targeted delivery window for the junction works Report P50
  • March 2027: CRSTS contractual commitment deadline Report P14, P36, P50

Plain English for the jargon

  • CYCLOPS: A junction arrangement designed to separate cyclists from motor traffic, with a cycle track wrapping around the outside of the junction.
  • CRSTS: City Region Sustainable Transport Settlements, a government funding programme for transport schemes.
  • MCF: Mayoral Challenge Fund, a Transport for Greater Manchester funding stream for cycling and walking infrastructure.
  • TfGM: Transport for Greater Manchester, the regional transport authority.
  • Lot 1 of the Bolton Highways Framework: A pre-approved framework agreement used by the Council to procure highway works from experienced contractors.
  • Section 106: A planning obligation under Section 106 of the Town and Country Planning Act 1990, requiring a developer to contribute to infrastructure.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5l

Resolved

Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby approve: · to go out to competition for the procurement of the Chapel Street/ Trinity Way Junction CRSTS works: · the Chapel Street/ Trinity Way junction CRSTS works to be procured in accordance with the Council’s Contract Procedure Rules through the Bolton Highways Framework. · authority is delegated to the Deputy Chief Executive (Executive Director Place) in consultation with the Lead Member for Planning, Transport and Sustainable Development to approve the submission of a business case to Transport for Greater Manchester for the Chapel Street/ Trinity Way CRSTS scheme. The Reasons are : To enable a competitive tender process to be undertaken for the Chapel Street/ Trinity Way CRSTS junction works. Options considered and rejected were : Direct award of works. Assessment of Risk : High – Salford has Programme Entry approval for the scheme and requires that this is contractually committed by March 2027. The delivery of the scheme needs to be co-ordinated with other projects in the locality to avoid severe highway network congestion during the construction. The source of funding is : CRSTS Streets for All Programme / Section 106 Contribution. Legal Advice obtained : Rebecca Maddison, 03/03/26. Financial Advice obtained : Grace Rogerson, 05/03/26. Procurement Advice obtained: Heather Stanton, 03/03/26. HR Advice obtained: N/A. Climate Change Implications obtained: N/A. The following documents have been used to assist the decision process: · Report of the Deputy Chief Executive (Executive Director of Place) to the Procurement Board on 23 rd March 2026. · Report of the Strategic Director Place to the Lead Member for Planning, Transport and Sustainable Development (Part 2) on 9 th July 2025. · Report of the Strategic Director Place to the Lead Member for Planning, Transport and Sustainable Development (Part 2) on 15 th February 2022. Contact Officer: Opu Anwar Contact e-mail: [email protected] · This matter is not subject to consideration by another Lead Member. · The appropriate Scrutiny Committee to call-in the decision is the Growth and Prosperity Scrutiny Panel. Signed: Paul Dennett Dated: 23 March 2026. City Mayor FOR DEMOCRATIC SERVICES USE ONLY: * This decision was published on 24 March 2026. * This decision will come in force at 4.00 p.m. on 31 March 2026 unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

1. That Procurement Board / Paul Dennett, City Mayor, to grant authority for the Chapel Street / Trinity Way junction CRSTS works to be procured in accordance with the Council’s Contract Procedure Rules through the Bolton Highways Framework.

2. That Procurement Board delegates authority to the Deputy Chief Executive (Executive Director Place) in consultation with the Lead Member for Planning, Transport and Sustainable Development to approve the submission of a business case to Transport for Greater Manchester for the Chapel Street / Trinity Way CRSTS scheme.

Executive summary

The purpose of this report is to request approval to go out competition for the delivery of the Chapel Street / Trinity Way junction CRSTS works so as to allow a business case to be completed and for the delivery of the works to be co-ordinated with other projects in the locality.

BACKGROUND DOCUMENTS:

Report of the Strategic Director Place to the Lead Member for Planning, Transport and Sustainable Development (Part 2) on 15th February 2022

Sample A – going out to tender Report of the Strategic Director Place to the Lead Member for Planning, Transport and Sustainable Development (Part 2) on 9th July 2025

KEY DECISION: Yes

DETAILS:

Project Summary

The junction of Trinity Way and Chapel Street is a gateway to the city centre and is at the intersection of a number of key links on the City Centre Bee Network. The junctions’ proximity to Salford Central Railway Station, and position on a key bus corridor, also means it is used by local communities accessing public transport.

The junction is a key access point to Salford city centre and forms part of the wider walking and cycling network serving local communities as well as wider traffic movement. The junction currently has no controlled crossings on the two Chapel Street arms, and a deteriorating carriageway surface. These conditions create safety and accessibility issues for people moving between Chapel Street, Trinity, Islington and the city centre.

A CYCLOPS arrangement was developed using MCF development funding for this junction however cannot progress at this time due to unresolved concerns about traffic impacts and the need for alignment with the emerging City Centre Movement Strategy. The junction does require intervention in the short term due to its poor condition and the absence of full controlled pedestrian crossings. An interim scheme is therefore required to resurface the junction and introduce new controlled pedestrian facilities on Chapel Street.

Following acceptance at programme entry stage a business case is currently under development to secure funding for scheme delivery from the CRSTS Streets for All programme.

A critical consideration for the scheme is the delivery timetable. The CRSTS programme requires contractual commitment for projects by March 2027 however co-ordination is required with another one of Salford’s Active Travel schemes as well as a major scheme to be delivered by Manchester Council early in 2027. To that end, it is critical that the Chapel Street / Trinity Way scheme is delivered as soon as practical to try and remove the possible impacts of these nearby works taking place at the same time.

As the interim scheme will not provide the same level of benefits to cyclists as the MCF scheme, a complementary package of works to strengthen parallel cycle routes is being considered. This will be subject to a separate procurement route and should this require Procurement Board approval, a further report will be submitted.

Procurement

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to go out to tender/ competition for Chapel Street/ Trinity Way Junction Procurement (Opu Anwar)Report 83 KB DownloadRead as text

At this meeting

Whole meeting
3To approve, as a correct record, the minutes of the meeting held on Monday 9 March 2026On the agenda 5aApproval to go out to tender for the Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Approved 5bApproval to Award the Contract for the Salford Healthy Child Programme, 0-19 Service (Gillian McLauchlan)On the agenda 5cAllied Health Professional Contract (Debbie Blackburn)Approved 5dApproval to go out to competition for Utility Coring Contract (Lee Lacking)Approved 5eThe purchase of three ex-demonstration Schmidt Swingo Road Sweepers from the NEPO Framework Agreement (Alan Fitzsimons)Approved 5fApproval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)Approved 5gApproval to go out to tender for the delivery of Bikeability 2026-2029 (Simi Drummond)Approved 5hApproval for an Extension of Contract for Occupational Health Services - Greater Manchester Collaboration OH Services (Optima Health) (Karen Bird)Approved 5iApproval to the extension of the contract for Arboricultural Services (Jo Regan/ Ian Worsley/ Paul Jones)Approved 5jApproval to Award the Contract for renewal of non-half hourly (NHH) electricity supply (Majid Maqbool)Approved 5kApproval to Award the Unmetered Public Lighting Electricity contract (Majid Maqbool)Approved
5lApproval to go out to tender/ competition for Chapel Street/ Trinity Way Junction Procurement (Opu Anwar)This decision
5mPrimrose Hill Primary School, Increase in Construction Costs (Sean Leah/ Tracey Squirrell)Approved 8aApproval to Award the Contract for the Salford Healthy Child Programme, 0-19 service (Gillian McLauchlan)Approved 8bApproval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)Approved

Who was there

5 of 8 attended
JC
Jim CammellInvitee, in attendance
PD
Paul DennettCommittee Member, apologies due to council business
AH
Anthony HiltonOfficer, present
CH
Chris HowlClerk, present
TK
Tracy KellyCommittee Member, apologies
JM
John Merry CBECommittee Member, present
TP
Teresa PepperCommittee Member, present
JY
Jack YoudChair, present

On this subject at Salford

Search all
  1. Approval to go out to tender/ competition for Chapel Street/ Trinity Way Junction Procurement (Opu Anwar)This decision
  2. Approval to go out to tender for a Management Information System for Regulatory Services, Vehicle Management Services, Waste Management Services and the Customer Contact Centre (Tim Cook)Approved
  3. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved
  4. Approval to go out to tender/ competition for S2007 – Floating Wetlands Habitats (Andrew Chatterjee/ Opu Anwar)Approved
  5. Approval to go out to tender/ competition for Ordsall Neighbourhood Scheme (Anene Chiegboka)Approved
  6. Approval to go out to competition for Adult Social Care Business Delivery Partners (Matt Drogan)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open