Procurement Board, Monday 23 March 2026 at 2.00pm

Primrose Hill Primary School, Increase in Construction Costs (Sean Leah/ Tracey Squirrell)

Approved Committee 1 paper

AI summarySalford City Mayor approves £547,868 increase in construction costs at Primrose Hill Primary School, varying the Seddon Construction contract. Total project cost rises to £5,763,900, funded by the Basic Need grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedVariation to Seddon Construction contract approved
Money£547,868 increaseTotal project cost £5,763,900, Basic Need grant
What happens nextContract varied for additional worksCompletion due by 01/10/2026
Who it affectsPrimrose Hill Primary School, Ordsall wardChildren's Services, additional pupils

What was decided

The City Mayor accepted the Procurement Board recommendation to grant an exception to Contractual Standing Orders and award a £547,868 increase in construction costs to Seddon Construction Limited for Primrose Hill Primary School. Report P1, P4

The exception is justified on the grounds that the award delivers Best Value to the Council, with no options considered and rejected. Report P5, P6

The total Seddon Construction contract value becomes £5,179,064, with full development project costs of £5,763,900 including council fees, surveys and risk. Report P4, P5, P36

Why

Additional unforeseen drainage works, including an attenuation tank, hydrobrake and extra manholes, plus larger playground resurfacing, have driven extra design and build costs. Report P18, P19

Prolongation and subsequent inflation costs have been incurred by the Design and Build Contractor as a result of these design changes. Report P19

Risk is assessed as high: failure to complete on time could leave the city council unable to provide sufficient school places. Report P23, P24

What happens next

The contract with Seddon Construction Limited will be varied to include the additional works and costs, permissible under Regulation 72 of the Public Contracts Regulations 2015 as the increase stays within 50% of the original value. Report P29, P30, P32, P38

Works continue under the existing contract running to 01/10/2026, with procurement implications confirmed compliant with PCR and the Council's own Contractual Standing Orders. Report P4, P38

The money

  • £547,868 Increase in construction costs requested in this report Report P35
  • £5,179,064 Total Seddon Construction contract value including this increase Report P5, P36
  • £5,763,900 Full development project costs, including SCC fees, surveys and risk Report P5, P36
  • £584,836 Surveys, professional fees, clearance and associated costs Report P36

Options considered

  • Chosen: Exception to Contractual Standing Orders to vary the Seddon Construction contract for the additional drainage and resurfacing works. Delivers Best Value to the Council and avoids re-procurement; permissible under PCR 2015 Regulation 72 as the increase is within 50% of the original contract value Report P5, P29, P32, P38
  • Rejected: Other options considered and rejected. None stated; the decision record says no options were considered and rejected

Implications

  • Financial: Additional £547,868 funded from the Basic Need grant allocation, recognised within the Children's Service Capital Programme. Report P26, P34, P35, P36
  • Legal: Variation assessed as permissible under Public Contracts Regulations 2015, Regulation 72, with risk of challenge considered relatively low. Report P30, P33
  • Risk: High risk that delay could leave the city council failing to provide sufficient school places; programme developed to meet earliest completion dates. Report P23, P24
  • Equalities: No equality impact assessment implications identified. Report P22
  • Staffing: No HR implications. Report P39
  • Climate: No significant climate change implications; projects must support the Council's carbon neutral by 2038 objective. Report P40, P41

Who and where

  • Pupils and parents at Primrose Hill Primary School (Ordsall ward), as additional modular and classroom accommodation is delivered Report P21, P45
  • Children's Services lead service group Report P4, P5
  • Seddon Construction Limited, as the existing contractor Report P3, P4

Timeline

  • 18th April 2024: Lead Member report approving indicative budget costs for additional capacity at Primrose Hill Community Primary School Report P10
  • May 2024: Children's Services approved Seddon Construction Limited as Contractor Partner for Design to RIBA Stage 4 under Stage 1 tender Report P15
  • 03/06/2024: Contract start date Report P4, P5
  • 14th July 2025: Procurement Board report on approval to award the temporary classroom accommodation contract Report P11
  • 18th August 2025: Procurement Board approved award of the Stage 2 modular accommodation contract Report P12, P17
  • 20.01.2026: Financial implications supplied by the Accountant Report P34
  • 23/03/2026: Procurement Board considers the increase in construction costs
  • 01/10/2026: Contract end date Report P4, P5

Plain English for the jargon

  • CSO (Contractual Standing Orders): The Council's own rules governing how contracts must be procured and awarded.
  • PCR 2015 Regulation 72: A rule under the Public Contracts Regulations 2015 that allows an existing contract to be modified without re-procurement in defined circumstances, including certain unforeseen additional works, provided any price rise does not exceed 50% of the original value.
  • Basic Need grant: Government funding allocated to councils to provide sufficient school places.
  • RIBA Stage 4: Royal Institute of British Architects design stage covering technical design before construction.
  • North West Construction Hub Framework: A procurement framework used by the Council to call off construction services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5m

Resolved

Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby approve: · an exception to Contractual Standing Orders to award a contract for increase in construction costs for Primrose Hill Primary School, as detailed in the table below: Detail required Answers Primrose Hill Primary School Title/Description of Contracted Service/Supply/Project Increase in Construction Costs for Primrose Hill Primary School Procurement Reference Number (DN and CR, supplied by Procurement) Name of Successful Contractor Seddon Construction Limited Supplier Registration Number (to be supplied by Procurement) 03578140 Proclass Classification No. (to be completed by procurement) Type of organisation (to be supplied by Procurement) Private Limited Company Status of Organisation (to be supplied by Procurement) Non-SME Contract Value (£) £547,868 construction costs Total Contract Value including extensions (£) £5,179,064 Seddon Construction Value £5,763,900 Full Development Project costs inclusive of SCC Fees, Surveys, Risk etc Contract Duration 28 months Contract Start Date 03/06/2024 Contract End Date 01/10/2026 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Adam Vanden Lead Service Group Children's Services Reason for CSO Exception: The goods / services / works are only obtainable from one provider and there is no other provider available to allow genuine competition Tick if it applies ? Reason for CSO Exception: The execution of works or the supply of goods or services is controlled by a statutory body Tick if it applies ? Reason for CSO Exception: Delivers Best Value to the Council Tick if it applies ? Reason for CSO Exception: Special education, health or social care contracts, if it is considered in the Council’s best interests and to meet the Council’s obligations under relevant legislation Tick if it applies ? Reason for CSO Exception: The execution of works or the supply of goods and services is required so urgently as not to permit compliance with the requirements of competition Tick if it applies ? Reason for CSO Exception: Security works where the publication of documents or details in the tendering process could prejudice the security of SCC and Salford residents Tick if it applies ? The reasons are : to provide modular accommodation and ancillary to accommodate the additional pupils attending the school. Options considered and rejected were : None. All procedures are in accordance with normal standing orders. Assessment of risk : High. Failure to complete the works within the timescales could result in the city council failing to provide sufficient school places. The source of funding is : Basic Need grant allocation. Legal advice obtained: Tony Hatton, Solicitor The main contract to appoint Seddon Construction Limited to progress classroom accommodation and modular units at Primrose Hill PS followed and exercise to call off the North West Construction Hub Framework , approved by Procurement Board and City Mayor in July and August 2025. For the reasons set out in the report, additional, unforeseen works and ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That the Procurement Board recommends Councillor Youd, Lead Member for Finance and Support Services and chairman of the Procurement Board, approves an exception to Contractual Standing Orders as permitted within the City Council Constitution for the reason(s) highlighted in the table below and the award of the Contract for increase in Construction Costs for the Primrose Hill Primary School as detailed in the table below:

Detail required Answers Title/Description of Contracted Service/Supply/Project Primrose Hill Primary School

Procurement Reference Number (DN Increase in Construction Costs for Primrose Hill and CR, supplied by Procurement) Primary School Name of Successful Contractor Seddon Construction Limited Supplier Registration Number 03578140 (to be supplied by Procurement) Proclass Classification No. (to be completed by procurement)

Type of organisation Private Limited Company (to be supplied by Procurement) Status of Organisation Non-SME (to be supplied by Procurement) Contract Value (£) £547,868 construction costs

Sample C – Exception to CSO’S Detail required Answers Total Contract Value including £5,179,064 Seddon Construction Value extensions (£) £5,763,900 Full Development Project costs inclusive of SCC Fees, Surveys, Risk etc Contract Duration 28 months Contract Start Date 03/06/2024 Contract End Date 01/10/2026 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Executive Director (extension < £150k) Period? Contact Officer (Name & number) Adam Vanden Lead Service Group Children's Services Reason for CSO Exception: The Tick if it applies ☐ goods / services / works are only obtainable from one provider and there is no other provider available to allow genuine competition Reason for CSO Exception: The Tick if it applies ☐ execution of works or the supply of goods or services is controlled by a statutory body Reason for CSO Exception: Delivers Tick if it applies ☒ Best Value to the Council Reason for CSO Exception: Special Tick if it applies ☐ education, health or social care contracts, if it is considered in the Council’s best interests and to meet the Council’s obligations under relevant legislation Reason for CSO Exception: The Tick if it applies ☐ execution of works or the supply of goods and services is required so urgently as not to permit compliance with the requirements of competition Reason for CSO Exception: Security Tick if it applies ☐ works where the publication of documents or details in the tendering process could prejudice the security of SCC and Salford residents

Sample C – Exception to CSO’S Detail required Answers Reason for CSO Exception: Tick if it applies ☐ Procurements made through, or on behalf of, any consortium, local authority, statutory or similar body, provided that tenders or quotations are invited and contracts placed in accordance with national or EU legislation.

Funding Source Grant Ethical Contractor (EC): Mayor’s Yes Employment Charter EC: Committed to sign up to the N/A Mayor’s Employment Charter EC: Committed to the principles N/A outlined in the Mayor’s Employment charter EC: Accredited Living Wage Yes Employer EC: Committed to becoming N/A Accredited Living Wage Employer

Executive summary

The purpose of this report is to request an exception to Contractual Standing Orders to approve the award of a contract for (insert title of project/scheme/service or purchase of goods)

BACKGROUND DOCUMENTS:

Report to Lead Member for Children’s and Young People’s Services Briefing dated 18th April 2024 titled Approval of indicative budget costs for the creation of additional capacity at Primrose Hill Community Primary School

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Primrose Hill Primary School, Increase in Construction Costs (Sean Leah/ Tracey Squirrell)Report 157 KB DownloadRead as text

At this meeting

Whole meeting
3To approve, as a correct record, the minutes of the meeting held on Monday 9 March 2026On the agenda 5aApproval to go out to tender for the Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Approved 5bApproval to Award the Contract for the Salford Healthy Child Programme, 0-19 Service (Gillian McLauchlan)On the agenda 5cAllied Health Professional Contract (Debbie Blackburn)Approved 5dApproval to go out to competition for Utility Coring Contract (Lee Lacking)Approved 5eThe purchase of three ex-demonstration Schmidt Swingo Road Sweepers from the NEPO Framework Agreement (Alan Fitzsimons)Approved 5fApproval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)Approved 5gApproval to go out to tender for the delivery of Bikeability 2026-2029 (Simi Drummond)Approved 5hApproval for an Extension of Contract for Occupational Health Services - Greater Manchester Collaboration OH Services (Optima Health) (Karen Bird)Approved 5iApproval to the extension of the contract for Arboricultural Services (Jo Regan/ Ian Worsley/ Paul Jones)Approved 5jApproval to Award the Contract for renewal of non-half hourly (NHH) electricity supply (Majid Maqbool)Approved 5kApproval to Award the Unmetered Public Lighting Electricity contract (Majid Maqbool)Approved 5lApproval to go out to tender/ competition for Chapel Street/ Trinity Way Junction Procurement (Opu Anwar)Approved
5mPrimrose Hill Primary School, Increase in Construction Costs (Sean Leah/ Tracey Squirrell)This decision
8aApproval to Award the Contract for the Salford Healthy Child Programme, 0-19 service (Gillian McLauchlan)Approved 8bApproval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)Approved

Who was there

5 of 8 attended
JC
Jim CammellInvitee, in attendance
PD
Paul DennettCommittee Member, apologies due to council business
AH
Anthony HiltonOfficer, present
CH
Chris HowlClerk, present
TK
Tracy KellyCommittee Member, apologies
JM
John Merry CBECommittee Member, present
TP
Teresa PepperCommittee Member, present
JY
Jack YoudChair, present

On this subject at Salford

Search all
  1. Primrose Hill Primary School, Increase in Construction Costs (Sean Leah/ Tracey Squirrell)This decision
  2. Approval of revised indicative budget costs for expansion work, at Ellesmere Park High School and Primrose Hill Primary SchoolApproved
  3. Approval of indicative budget costs for the creation of additional capacity at Primrose Hill Community Primary School (Paula Newall)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies