Approval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)

Approved Committee 1 paper

AI summarySalford awards the Islington Active Neighbourhood contract to Argyle North West Construction Ltd at £851,002.73, with works due to run from 27 July to 30 October 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to TfGM and Bee Network Committee approvals
Money£851,002.73 plus £127,650 risk allowanceFunded from Active Travel Fund Tranche 4 grant
What happens nextContract runs 27/07/2026 to 30/10/2026Approximately 14 weeks
Who it affectsIslington area and city centre accessWalking, cycling and local traffic

What was decided

Councillor Youd accepted the Procurement Board's recommendation to appoint Argyle North West Construction Ltd, subject to business case approval by TfGM's Active Travel Programme Board and funding approval by the Bee Network Committee.

A purchase order to the contractor, to the value of £851,002.73, was approved to enable payments.

Use of the £127,650 risk allowance budget towards associated project delivery expenditure was approved.

Why

The Salford City Centre Bee Network will upgrade walking, wheeling and cycling links through Islington, improving safe access to the city centre.

The scheme will deliver new cycle facilities, better crossings, modal filters and public realm enhancements to reduce through-traffic while maintaining local access.

Awarding the delivery contract is needed to progress an active travel scheme that supports safer streets, sustainability and reduced traffic congestion.

What happens next

The contract is scheduled to run from 27/07/2026 to 30/10/2026, approximately 14 weeks.

TfGM's Active Travel Programme Board must approve the business case, and the Bee Network Committee must approve funding before the appointment takes effect.

The money

  • £851,002.73 Purchase order value for the delivery contract with Argyle North West Construction Ltd
  • £127,650 Risk allowance budget for associated project delivery expenditure

Options considered

  • Rejected: No alternative options were considered and rejected. The decision record states 'None' for options considered and rejected.

Implications

  • Risk: Risk is assessed as low because contractors on the Bolton Highways Framework Contract have a successful track record of delivering schemes for the council.
  • Legal: Legal advice was obtained from Tony Hatton, Principal Solicitor.
  • Financial: Financial advice was obtained from Ian Cowburn, Senior Accountant; the funding source is the Active Travel Fund Tranche 4 grant.
  • Other: Procurement advice was obtained from Heather Stanton, Category Manager.

Who and where

  • Residents, pedestrians and cyclists in the Islington area of Salford city centre
  • Motorists using Islington, who may see through-traffic reduced
  • Visitors and workers accessing Salford city centre

Timeline

  • 23/03/2026: Procurement Board meeting; decision approved by Councillor Youd Report P3, P4
  • 27/07/2026: Contract start date
  • 30/10/2026: Contract end date

Plain English for the jargon

  • CCBN: City Centre Bee Network, Salford's active travel programme
  • TfGM: Transport for Greater Manchester
  • Bee Network Committee: Committee responsible for Greater Manchester's Bee Network active travel funding
  • Modal filter: A physical feature that restricts motor vehicle access while permitting walking and cycling
  • ITT: Invitation to Tender
  • SME: Small and Medium-sized Enterprise
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8b

Resolved

Salford City Council – Record of Decision I Councillor Youd, Lead Member for Finance and Support Services and chairman of the Procurement Board, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby approve: 1) Approve the appointment of Argyle North West Construction Ltd, subject to business case approval by TfGM’s Active Travel Programme Board and funding approval by the Bee Network Committee. 2) Approve the creation of a purchase order to Argyle North West Construction Ltd, to the value of £851,002.73 which will enable payments to be made to the contractor. 3) Approve the utilisation of the £127,650 risk allowance budget towards associated project delivery expenditure. Detail required Answers Title/ Description of Contracted Service/Supply/Project City Centre Bee Network: Islington Procurement Reference numbers (DN and CR number supplied by Procurement) S1869 Name of Successful Contractor Argyle North West Construction Ltd Supplier Registration Number (to be supplied by Procurement 02829893 Proclass Classification No. (to be completed by procurement) 391410 Type of organisation (to be supplied by Procurement) Private Limited Company Status of Organisation (to be supplied by Procurement) SME Contract Value (£) £ 851,002.73 Total contract value £ (including extensions) NA Contract Duration Approx. 14 weeks Contract Start Date 27/07/2026 Contract End Date 30/10/2026 Optional Extension Period 1 N/A Optional Extension Period 2 N/A Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Assad Khalid Lead Service Group Place How the contract was procured? (to be supplied by procurement) ITT Framework Details (where applicable) (procurement body, framework reference & title, start/ end date Bolton Highways Framework Contract 2024 – 2028 LOT 1 – General Civil Engineering Works Funding Source Active Travel Fund Tranche 4 Ethical Contractor (EC): Mayor’s Employment Charter Yes EC: Committed to sign The Mayor’s Employment Charter Choose an item. EC: Committed to the principles outlined in the Mayor’s Employment charter Choose an item. EC: Accredited Living Wage Employer Yes EC: Committed to becoming Accredited Living wage Employer Choose an item. ? The Reasons are : The Salford City Centre Bee Network will upgrade walking, wheeling and cycling links through the Islington area, improving safe access to the city centre. The scheme deliver will new cycle facilities, better crossings, modal filters, and public?realm enhancements to reduce through?traffic while maintaining local access. Approval is required to award the delivery contract, enabling progress on a key active?travel scheme that supports safer streets, sustainability, and eliminates traffic congestion within the neighbourhood. Options considered and rejected were : None Assessment of Risk : Low - the contractors on the Bolton Highways Framework Contract have a successful track record of delivering schemes on behalf of the City Council. The source of funding is Active Travel Fund Tranche 4 grant Legal Advice obtained : Yes – received from Tony Hatton, Principal Solicitor. Financial Advice obtained : Yes – received from Ian Cowburn, Senior Accountant. Procurement Advice obtained: Yes – received from Heather Stanton, Category Manager. Climate Change Implications obtained: ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

PUBLIC INTEREST TEST – CHECKLIST Schedule 12A Local Government Act 1972

Name of Report: Approval to Award Contract for CCBN Islington Active Neighbourhood Scheme

Committee: Procurement Board

Date: 23 March 2026

Category of exemption applied (from list below): 7a

1 Information relating to any individual 2 Information which is likely to reveal the identity of any individual 3 Information relating to the financial or business affairs of any particular person (including the Authority holding that information) 4 Information relating to any consultations or negotiations, or contemplated consultations or negotiations, in connection with any labour relations matter arising between the Council, or a Government minister, and any employees of, or office holders under, the Council. 5 Information in respect of which a claim to legal professional privilege could be maintained in legal proceedings. 6 Information which reveals that the Council proposes:

a) give under any enactment a notice under or by virtue of which requirements are imposed on a person (including an organisation) or

b) to make an order or direction under any enactment 7 Information relating to any action taken or to be taken in connection with the prevention, investigation or prosecution of crime.

Standards Committee Only 7a Information which is subject to any obligation of confidentiality 7b Information which relates in any way to matters concerning national security 7c The deliberations of a standards committee or of sub-committee of a standards committee established under the Provisions of part III of the Local government Act 2000 in reaching any finding on any matter referred under the provisions of section 64(2) of 71(2) of the Local Government Act 2000 Public Interest Test Questionnaire This is not a definitive list. However, it does provide a series of questions that you should ask yourself when recommending confidentiality.

FACTORS WHICH SUPPORT DISCLOSING INFORMATION Will disclosure help people to understand and participate in public debate about current issues?

Sufficient detail is provided in the Part 1 report to enable informed public discussion of the decision, and the required public engagement and Statutory consultation on the proposed Traffic Regulation Order advertising, which has already taken place. The Part 2 report contains information that is commercially sensitive.

Will disclosure help people to understand why the Council has taken certain decisions?

No - There is sufficient information available in the Part 1 report.

Will disclosure give the public information about the personal probity (or otherwise) of elected members or council staff?

No information is provided on this matter in the reports.

Will disclosure encourage greater competition and better value for money for council taxpayers?

No – Disclosing commercially sensitive contingency information would not improve value for money for council taxpayers.

Will disclosure allow individuals and companies to understand decisions made by the Council that have affected their lives?

No - There is sufficient information available in the Part 1 report.

Is the information about factors that affect public health and public safety? (NB you should be careful if considering the release of information which might adversely affect public health and safety)

No information is provided on this matter in the reports.

Will disclosure reveal incompetent, illegal or unethical decision- making or examples of malpractice?

Not applicable Will disclosure reveal that such maladministration has not in fact occurred?

Not applicable FACTORS WHICH SUPPORT WITHHOLDING INFORMATION Will disclosure damage the Council’s interests without giving the public any useful information?

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)Report 70 KB DownloadRead as text

At this meeting

Whole meeting
3To approve, as a correct record, the minutes of the meeting held on Monday 9 March 2026On the agenda 5aApproval to go out to tender for the Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Approved 5bApproval to Award the Contract for the Salford Healthy Child Programme, 0-19 Service (Gillian McLauchlan)On the agenda 5cAllied Health Professional Contract (Debbie Blackburn)Approved 5dApproval to go out to competition for Utility Coring Contract (Lee Lacking)Approved 5eThe purchase of three ex-demonstration Schmidt Swingo Road Sweepers from the NEPO Framework Agreement (Alan Fitzsimons)Approved 5fApproval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)Approved 5gApproval to go out to tender for the delivery of Bikeability 2026-2029 (Simi Drummond)Approved 5hApproval for an Extension of Contract for Occupational Health Services - Greater Manchester Collaboration OH Services (Optima Health) (Karen Bird)Approved 5iApproval to the extension of the contract for Arboricultural Services (Jo Regan/ Ian Worsley/ Paul Jones)Approved 5jApproval to Award the Contract for renewal of non-half hourly (NHH) electricity supply (Majid Maqbool)Approved 5kApproval to Award the Unmetered Public Lighting Electricity contract (Majid Maqbool)Approved 5lApproval to go out to tender/ competition for Chapel Street/ Trinity Way Junction Procurement (Opu Anwar)Approved 5mPrimrose Hill Primary School, Increase in Construction Costs (Sean Leah/ Tracey Squirrell)Approved 8aApproval to Award the Contract for the Salford Healthy Child Programme, 0-19 service (Gillian McLauchlan)Approved
8bApproval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)This decision

Who was there

5 of 8 attended
JC
Jim CammellInvitee, in attendance
PD
Paul DennettCommittee Member, apologies due to council business
AH
Anthony HiltonOfficer, present
CH
Chris HowlClerk, present
TK
Tracy KellyCommittee Member, apologies
JM
John Merry CBECommittee Member, present
TP
Teresa PepperCommittee Member, present
JY
Jack YoudChair, present

On this subject at Salford

Search all
  1. Approval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)This decision
  2. Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Approved
  3. Approval to Award the Contract for the continued use of the Line of Business System for Planning, Building Control and Local Land and Property Gazetteer (Anthony Stephenson)Approved
  4. Approval to Award the Contract for Statutory Homeless Supported Temporary Accommodation (Jane Barlow)Approved
  5. Approval to Award the Contract for the construction of affordable homes at Robert Hall St Ordsall (A2) Dylan VinceApproved
  6. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open