Resolved – That a new call for bids be approved as set out in Appendices 1 to 3 to the report and per the agreed LGF prioritisation methodology, subject to the amendment agreed on the eligibility criteria, and further refinement of the weightings and timescales.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. Following the successful bidding and allocation of both Local Growth Fund (LGF) monies (2015-2021) and Business Rates Retention Pilot (BRRP) monies (2018-2020) across Thames Valley Berkshire, this report sets out the requirements to create a new call for bids in order to meet anticipated additional funding being made available for Berkshire.
2. At this point, the amount, and source, of funding is to be confirmed, but it may come from reallocation of existing LGF or BRRP scheme monies or new funding sources (e.g. UK Shared Prosperity Fund).
3. As specified in the BLTB Assurance Framework 4.0, the BLTB will issue a call for capital schemes, including eligibility criteria:
• a minimum threshold value in order to encourage major schemes • a minimum level of detail in order to be able to establish the nature, purpose and content of the scheme • a minimum matching funding percentage in order to ensure local commitment to the scheme Schemes which do not meet the eligibility criteria may be refused entry to the programme, or referred back to the promoter for further development.
4. This report sets out the detailed arrangements for assessing and prioritising potential projects based upon the changes to the Prioritisation Methodology approved at your July 2019 meeting, item 101.
Item 5: BLTB 14 November 2019 Thames Valley Berkshire Call for Bids – Process Recommendation
5. You are recommended to approve a new call for bids as set out in Appendices 1 to 3 and per the agreed LGF prioritisation methodology.
Background
6. In March 2018, the BLTB approved a new call for bids, in advance of the new BRRP. The process allowed for existing LGF projects to have their funding replaced with BRRP funds, thus freeing up LGF in the process. The call for bids therefore sought bids for the BRRP and replacement LGF schemes. A new pipeline was created for both funding streams and in July 2018, programme entry status was awarded to three schemes. In January 2019, LGF for the 2.14 &/ 2.25 East Reading MRT scheme was withdrawn. At the extraordinary BLTB meeting in January 2019, Programme Entry Status was awarded to six new LGF projects utilising the withdrawn funds and a further scheme in March 2019. These instances have resulted in the top ten of the LGF pipeline created in July 2018 being awarded funding.
7. In November 2018 and January 2019, each of the six Unitary Authorities were awarded £100,000 revenue funding from the BRRP, in order to help develop business cases for future projects. This work is progressing, and it is expected that new business cases should be ready shortly.
8. In addition, Transport Officers have been creating a long list of indicative future schemes, should future funding become available.
Other Implications
Financial
9. The lead authority for the control of Local Growth Funds allocated to infrastructure or regeneration projects is the Royal Borough of Windsor & Maidenhead, the LEP’s Accountable Body.
Risk management
10. The risks associated with large scale infrastructure investments are well known, and the BLTB has established risk management arrangements for the Local Growth Fund transport capital programme (£113m over six years), referred to as the BLTB Assurance Framework.
11. As part of the Local Growth Fund oversight a new BLTB Assurance Framework (Third Revision) was approved by the BLTB in July 2019, item 112.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.