Financial Approval 2.35 Reading: Reading West Railway Station Upgrade

Approved Committee 2 papers

Berkshire Local Transport Body approved this item on Thursday 14 November 2019. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

Resolved – That scheme 2.35 Reading: Reading West Station Update be given full financial approval in the sum of £3,100,000 over the period 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 of the report. The observations made by the Independent Assessor regarding delivery and timing risks were noted but it was believed that the existing conditions of the capital grant letter would enable the LEP to work closely with Reading Borough Council and the relevant partners to ensure timely delivery of the scheme.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To consider giving financial approval to scheme 2.35 Reading: Reading West Railway Station Upgrade.

2. The Reading West Station scheme will deliver an improved passenger experience and multi-modal interchange, including a new station building, highway changes and improvements to platform facilities and the Tilehurst Road entrance.

Recommendation

3. You are recommended to give scheme 2.35 Reading: Reading West Station Upgrade full financial approval in the sum of £3,100,000 over the period 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 below. We note observations made by the Independent Assessor regarding delivery and timing risks but believe that the existing conditions of our capital grant letter will enable us to work closely with Reading Borough Council and relevant partners to ensure timely delivery of the scheme.

Other Implications

Financial

4. A re-prioritisation exercise was undertaken in advance of previously allocated Growth Deal Funds and returned to the Growth Deal “pot” for re-allocation. Scheme 2.35 Reading: Reading West Railway Upgrade is funded from this reallocation.

5. This report recommends that Reading Borough Council be authorised to draw down the capital sum £3,100,000 from the Local Transport Body funding for this scheme, subject to usual capital grant letter conditions.

6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.

Risk management

7. The risk management arrangements already put in place by the Local Transport Body are as follows:

Item 6 BLTB 14 November 2019 Financial Approval 2.35 Reading West Railway Station Upgrade  The Assurance Framework1 has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes  Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme  The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.

Human Rights Act and Other Legal Implications

8. The scheme promoter is a local authority and they must act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.

Supporting Information

9. The scheme will be carried out by Reading Borough Council and Great Western Railway.

10. The full details of the scheme are available from the Reading Borough Council website2. A summary of the key points is given below:

Task Timescale Procurement May 2020 Construction start July 2020 Construction finish September 2021

Activity Funder Cost (approx) Local Growth Fund Berkshire Local Transport Body £3.10m Rail Industry Network Rail, GWR, DfT £940k Private sector funding s.106 £200k Total £4.24m

11. The table below sets out the details of this scheme’s compliance with steps1-5 of paragraph 14 of Assurance Framework3.

1http://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum 2http://info.westberks.gov.uk/sep 3http://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Approval 2.35 Reading: Reading West Railway Station UpgradeReport 143 KB DownloadRead as text
PDF
TVB LEP Independent Assessors Report: Reading West Station FBC (Ref 2.35)Report 360 KB Download

At this meeting

Whole meeting

Who was there

8 of 17 attended
RA
Councillor Robert AndersonCommittee Member, present
MB
Councillor Marc Brunel-Walker Bracknell Forest CouncilCommittee Member, present
GC
Councillor Gerry ClarkCommittee Member, present
PJ
Councillor Pauline JorgensenCommittee Member, apologies
TP
Councillor Tony Page Reading Borough CouncilChair, present
RS
Councillor Richard SomnerCommittee Member, present
SA
Stuart AtkinsonCommittee Member, apologies
CE
Charles EalesVice-Chair, apologies
MK
Malcolm KemptonCommittee Member, present
BM
Bob MountainCommittee Member, present
SR
Simon RatcliffeCommittee Member, apologies
MT
Matthew TaylorCommittee Member, present

All 17 on the meeting page

On this subject at Slough

Search all
  1. Financial Approval 2.35 Reading: Reading West Railway Station UpgradeThis decision
  2. Financial Approval: Scheme 2.37 Bracknell A322/A329 Corridor Improvements: Birch Hill Junction UpgradeApproved
  3. Financial Approval 2.47 Bracknell: Town Centre - "The Deck"Approved
  4. Financial approval GBF1 Slough: Langley High Street Widening Phase 3Approved
  5. Financial approval: Scheme 2.45 Langley High Street Widening Phase 2Approved
  6. Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban RealmApproved

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies