Resolved – That scheme 2.42 Wokingham: South Wokingham Distributor Road – Eastern Gateway be given full financial approval in the sum of £5,000,000 in 2019/20 on the terms of the funding agreement set out in paragraph 11 step 5 of the report.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme 2.42 Wokingham: South Wokingham Distributor Road – Eastern Gateway.
2. This project is part of the South Wokingham Distributor Road. The Eastern Gateway scheme will comprise a single carriageway distributor road connecting Montague Park with Waterloo Road, including a new road bridge over the Waterloo rail line.
3. This scheme is funded via the Business Rates Retention Pilot (BRRP).
Recommendation
4. You are recommended to give scheme 2.42 Wokingham: South Wokingham Distributor Road – Eastern Gateway full financial approval in the sum of £5,000,000 in 2019/20 on the terms of the funding agreement set out at paragraph 11 step 5 below.
Other Implications
Financial
5. This report recommends that Wokingham Borough Council be authorised to draw down the capital sum £5,000,000 from the Local Transport Body funding for this scheme.
6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
7. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Framework1 has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme
Item 8: BLTB 14 November 2019 Financial Approval Wokingham 2.42 South Wokingham Distributor Road: Eastern Gateway The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
8. The scheme promoter is a local authority and they have to act within the law. Wokingham Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
9. The scheme will be carried out for Wokingham Borough Council.
10. The full details of the scheme are available from the Wokingham Borough Council website2. A summary of the key points is given below:
Task Timescale Procurement Via the Council’s Term Contractor Contractor appointed As above Construction November 2019 Open to public November 2020
Activity Funder Cost (approx) Major scheme funding Berkshire Local Transport Body £5.0m Section 106 agreements Developers etc £15.159m Total £20.159m
11. The table below sets out the details of this scheme’s compliance with steps1-5 of paragraph 14 of Assurance Framework3.
Assurance Framework 2.42 South Wokingham Distributor Road – Eastern Gateway Check list Step 1: The scheme was originally developed by Wokingham Borough Council Development of in response to the growth pressures along this corridor, and in Scheme proposal; particular to developments at the former TRL site and Broadmoor. initial sifting, The SEP assessment process was used and the scheme was given scoring and 27.5 points and ranked 5 of 7 schemes submitted in BRRP. prioritisation Raw Weighted Factor Weighting leading to award of score score Programme Entry Strategy 3 1.5 4.5 Status. (See Deliverability 3 2.0 6.0 paragraphs 11-13) Economic Impact 3 4.0 12.0 TVB area coverage 2 1.5 3.0 Environment 1 0.5 0.5 Social 3 0.5 1.5
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.