Resolved
Resolved – That scheme 2.43 Wokingham Barkham Bridge be given full financial approval in the sum of £2,100,000 in 2019/20 and £2,135,641 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 of the report.
Berkshire Local Transport Body approved this item on Thursday 14 November 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That scheme 2.43 Wokingham Barkham Bridge be given full financial approval in the sum of £2,100,000 in 2019/20 and £2,135,641 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 of the report.
1. To consider giving financial approval to scheme 2.43 Wokingham Barkham Bridge.
2. The Barkham Bridge project consists of a new bridge structure across the Barkham Brook and approximately 300 metres of associated carriageway realignment. The new bridge is to be constructed south of the existing Barkham Bridge within private land. The existing Barkham Bridge Structure is to be retained and be converted to a shared footway/cycleway, connecting the existing sections of footway to the east and west.
3. You are recommended to give scheme 2.43 Wokingham Barkham Bridge full financial approval in the sum of £2,100,000 in 2019/20 and £2,135,641 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 below.
Other Implications
Financial
4. A re-prioritisation exercise was undertaken in advance of previously allocated Growth Deal Funds and returned to the Growth Deal “pot” for re-allocation. Scheme 2.43 Wokingham Barkham Bridge is funded from this reallocation.
5. This report recommends that Wokingham Borough Council be authorised to draw down the capital sum £4,235,641 from the Local Transport Body funding for this scheme.
6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Item 9: BLTB 14 November 2019 Financial Approval Wokingham 2.43: Barkham Bridge 7. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Framework1 has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes Hatch Regeneris has been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
8. The scheme promoter is a local authority and they have to act within the law. Wokingham Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
9. The scheme will be carried out for Wokingham Borough Council.
10. The full details of the scheme are available from the Wokingham Borough Council website2. A summary of the key points is given below:
Task Timescale Procurement Via the Council’s Term Contractor Contractor appointed As above Construction October 2019 Completion date March 2021
Activity Funder Cost (approx) Scheme development Wokingham Borough Council £3.44m Major scheme funding Berkshire Local Transport Body £4.24m Total £7.68m
11. The table below sets out the details of this scheme’s compliance with steps1-5 of paragraph 14 of Assurance Framework3.
Assurance Framework 2.43 Wokingham Barkham Bridge Check list Step 1: The scheme was originally developed by Wokingham Borough Council Development of to build a new bridge next to the existing Barkham Bridge (located
1 http://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum 2 https://www.wokingham.gov.uk/roadworks-and-outdoor-maintenance/major-new-roads/barkham-
bridge/ 3http://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Approval 2.43 Wokingham: Barkham BridgeReport | 155 KB | DownloadRead as text |
PDF |
TVB LEP Independent Assessors Report: Barkham Bridge FBC (Ref 2.43)Report | 310 KB | Download |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.