Resolved
Resolved – That the report be noted.
Berkshire Local Transport Body noted this item on Thursday 4 June 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the report be noted.
1. To review current information regarding the impact of Covid 19 on remaining Local Growth Fund infrastructure schemes.
2. To review completion dates of remaining Local Growth Fund (LGF) infrastructure schemes.
3. That this report be noted.
Other Implications
Financial
4. A full financial report will be submitted to the July 2020 Berkshire Local Transport Body meeting.
5. The 2020/21 LGF allocation for Thames Valley Berkshire LEP is £19,874,541. In May 2020 two thirds of this funding will be paid to the LEP’s Accountable Body, with the remaining third being held by government. This final third will be released pending evidence that schemes are contractually committed by September 2020 and able to receive final payments by March 2021.
Human Rights Act and Other Legal Implications
6. Slough Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
7. The UK Government’s position is to allow the construction and infrastructure industry to continue operating where it can do so safely.
8. Following the outbreak of the current Covid-19 pandemic, TVBLEP has been working closely with local transport officers to gauge the impact on extant schemes. 9. Whilst the situation continues to evolve, work continues on almost all schemes, albeit at a slower rate of progress, mainly driven by the 2-meter social distancing measures.
10. Whilst constant re-assessment of scheme progress continues, to this point we have not been informed of any significant project delay, although the true impact will only become apparent in the coming weeks.
11. Related to this situation is the impending conclusion by March 2021 of the LGF funding envelope. To summarise:
• LGF funds: all financial payments by the LEP must be completed by March 2021. • There a number of extant schemes that are scheduled to finish post March 2021. Of the 26 schemes currently in progress, 10 have post March ’21 completion dates – see table 1 below. • LEP guidance to officers has been to ensure scheme delivery is in calendar year 2021. • TVBLEP is working with our S151 officer to review possible Local Authority “capital swap” options for payment to schemes running past March 2021.
Table 1 Project Completion Scheme Name Promoter date
2.42Eastern Gateway (BRRP funded) WBC Apr-21 2.06 Green Park Station RBC May-21 2.05 Sandelford Park West Berks Sep-21 2.29 Winnersh Triangle P&R* WBC Sep-21 2.35 Reading West Station* RBC Sep-21 2.36 Coppid Beech P&R* WBC Oct-21 2.28 Bracknell A3095 BFC Nov-21 2.31 Slough Stoke Rd Regen SBC Mar-22
BLTB pending approvals June/July
2.40Windsor TC package* RBWM May-21 2.38 Theale Station upgrade* West Berks Dec-21 *These projects have not yet started on site.
Conclusion
12. TVBLEP will continue to work with Local Authority Transport Officers and other relevant parties to monitor remaining schemes and ensure timely delivery.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Covid 19 and Local Growth Fund timing updateReport | 91 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.