Berkshire Local Transport Body, Thursday 4 June 2020 at 4.00pm

Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride Addendums 1 Car Park enhancements

Approved Committee 1 paper

Berkshire Local Transport Body approved this item on Thursday 4 June 2020. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

Resolved – That scheme 2.29 be given financial approval in the sum of £715,444 in 2020/21 on the terms of the funding agreement set out in paragraph 11 step 5 of the report, subject to meeting the following conditions by 31 st July 2020: 1. Formal financial approval by Wokingham Borough Council for the allocated S106 scheme funding. 2. Formal financial approval by Wokingham Borough Council for any cost overruns, should they arise; and 3. Formal financial approval by Wokingham Borough Council for any loss of revenue resulting from the interim closure of the park and ride site during construction, should they arise.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To consider giving financial approval to an enhancement to scheme 2.29 Wokingham: Winnersh Triangle Park and Ride.

2. The original scheme sought to redevelop the transport links at Winnersh Triangle. The redevelopment will include double-decking the new park and ride site to add at least 250 additional car parking spaces, improvement of the station building including the surrounding area, reorganising the highways layout. These arrangements would complement growth plans of Frasers Property who are intensifying the use of Winnersh Triangle Business Park.

3. Since the original scheme was approved by the BLTB in March 2019, the following car park enhancements have been proposed:

3.1A requirement to replace the existing Sustainable Drainage System (SuDs) of the car park; 3.2. a new planning requirement to provide electric vehicle charging points; 3.3. a requirement to provide fully accessible access to the top-deck of the proposed car park deck; and 3.4. a requirement for additional unforeseen statutory undertaker’s works to move existing utilities.

Recommendation

4. You are recommended to give the car park scheme enhancement for scheme 2.29 Wokingham: Winnersh Triangle Park and Ride conditional financial approval in the sum in 2020/21:

4.1Car Park enhancements: of £715,444. It should be noted that programme entry status was awarded for £675,000

on the terms of the funding agreement set out at paragraph 11 step 5 below, subject to meeting the following conditions:

4.2Car Park enhancement conditions:

BLTB 4th June 2020 - Item 8: Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride Addendum 1 Car Park enhancements 1) Formal financial approval by Wokingham Borough Council for the allocated S106 scheme funding; 2) Formal financial approval by Wokingham Borough Council for any cost overruns, should they arise; and 3) Formal financial approval by Wokingham Borough Council for any loss of revenue resulting for interim closure of the park and ride site during construction, should they arise.

These conditions should be met no later than 31st July 2020.

Other Implications

Financial

5. A call for bids process was undertaken in January 2020 and a list of prioritised projects were agreed at the BLTB meeting March 2020. Scheme 2.29 Wokingham: Winnersh Triangle Park & Ride Addendums 1 Car Park enhancements was a named scheme.

6. This report recommends that the Wokingham Borough Council be authorised to draw down the capital sum £715,444 from the Local Transport Body funding for this scheme, subject to meeting the conditions set out in the recommendation.

7. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.

Risk management

8. The risk management arrangements already put in place by the Local Transport Body are as follows:  The Assurance Frameworki has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes  Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business cases for the scheme  The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.

Human Rights Act and Other Legal Implications

9. Slough Borough Council will provide legal support for the BLTB should any questions arise.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride Addendums 1 Car Park enhancementsAddendum 287 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 16 attended
RA
Councillor Robert AndersonCommittee Member, present
MB
Councillor Marc Brunel-Walker Bracknell Forest CouncilCommittee Member, present
GC
Councillor Gerry ClarkCommittee Member, present
PJ
Councillor Pauline JorgensenCommittee Member, present
TP
Councillor Tony Page Reading Borough CouncilChair, present
RS
Councillor Richard SomnerCommittee Member, present
SA
Stuart AtkinsonCommittee Member, present
CE
Charles EalesVice-Chair, present
MK
Malcolm KemptonCommittee Member, apologies
BM
Bob MountainCommittee Member, present
SR
Simon RatcliffeCommittee Member, apologies
MT
Matthew TaylorCommittee Member, apologies

All 16 on the meeting page

On this subject at Slough

Search all
  1. Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride Addendums 1 Car Park enhancementsThis decision
  2. Financial Approval: Scheme 2.37 Bracknell A322/A329 Corridor Improvements: Birch Hill Junction UpgradeApproved
  3. Financial Approval 2.47 Bracknell: Town Centre - "The Deck"Approved
  4. Financial approval GBF1 Slough: Langley High Street Widening Phase 3Approved
  5. Financial approval: Scheme 2.45 Langley High Street Widening Phase 2Approved
  6. Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban RealmApproved

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies