Resolved
Resolved – That the re-profiled scheme 2.37 Bracknell A322/A329 Corridor Improvements be given full financial approval in the sum of £400,000 in 2020/21 on the terms of the funding agreement set out in paragraph 11 step 5 of the report.
Berkshire Local Transport Body approved this item on Thursday 4 June 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the re-profiled scheme 2.37 Bracknell A322/A329 Corridor Improvements be given full financial approval in the sum of £400,000 in 2020/21 on the terms of the funding agreement set out in paragraph 11 step 5 of the report.
1. To consider giving financial approval to the re-profiled scheme 2.37 Bracknell: A322/A329 Corridor Improvements. This amended scheme focuses on the Bracknell Sports Centre Roundabout which forms part of an on-going wider programme of enhancements to the A322/A329 corridor that aligns well with the strategic priorities of the sub-region. In addition, it addresses localised issues of congestion at the junction.
2. You are recommended to give the re-profiled scheme 2.37 Bracknell: A322/A329 Corridor Improvements full financial approval in the sum of £400,000 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 below.
Other Implications
Financial
3. In January 2019, programme entry status was awarded to scheme 2.37 Bracknell A322/A329 Corridor Improvements and allocated £1,200,000. A further £800,000 was allocated at the July 2019i BLTB meeting, bringing the total funds allocated to the scheme to £2,000,000.
4. Notification was provided at the March 2020 BLTB meeting that scheme 2.39 Wokingham Coppid Beech Northbound On-Slip Widening was being withdrawn. Due to the linked nature of schemes 2.39 and 2.37, Bracknell Forest Council decided to reduce the scope of scheme 2.37 Bracknell A322/A329 Corridor Improvements. This reconfigured scheme is now requesting £400,000 of its original allocation of £2,000,000 to deliver part of the scheme.
5. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Item 5: BLTB 4 June 2020 Financial Approval 2.37 Bracknell A322/A329 Corridor Improvements – re-profiled 6. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Frameworkii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
7. The scheme promoter is a local authority and they have to act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
8. The scheme will be carried out for Bracknell Forest Council.
9. The full details of the scheme are available from the Bracknell Forest websiteiii. A summary of the key points is given below:
Task Timescale Procurement Via the Council’s Term Contractor Contractor appointed As above Construction January 2021 Completion March 2021
Activity Funder Cost (approx) Scheme development Bracknell Forest Council £117,658 Major scheme funding Berkshire Local Transport Body £400,000 Total £517,658
10. The table below sets out the details of this scheme’s compliance with steps1-5 of paragraph 14 of Assurance Frameworkiv.
Assurance 2.37 Bracknell A322/A329 Corridor Improvements – Framework re-profiled Check list The SEP assessment process was used and the original scheme was given 23.5 points and ranked 6th of 17 schemes submitted. Raw Weighted Factor Weighting score score Strategy 3 1.5 4.5 Deliverability 3 2.0 6.0 Economic Impact 2 4.0 8.0
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Approval 2.37 Bracknell: A322/ A329 Corridor Improvements: re-profiledReport | 241 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.