Resolved
Resolved – That Thames Valley Berkshire Smart City Cluster project extension be given full financial approval in the sum of £283,620 in 2020/21 on the terms of the funding agreement set out in paragraph 11 step 5 of the report.
Berkshire Local Transport Body approved this item on Thursday 4 June 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That Thames Valley Berkshire Smart City Cluster project extension be given full financial approval in the sum of £283,620 in 2020/21 on the terms of the funding agreement set out in paragraph 11 step 5 of the report.
1. To consider giving financial approval to the Thames Valley Berkshire Smart City Cluster project extension.
The Thames Valley Berkshire Smart City Cluster project extension will extend the existing Thames Valley Berkshire Smart City Cluster project by extending the Internet of Things (IoT) communications infrastructure (Long Range, Wide Area Network (LoRaWAN)) across Slough Borough Council (SBC) and the Royal Borough of Windsor and Maidenhead (RBWM) with a small element of development work to be undertaken by Reading Borough Council (RBC) to further develop the LoRa to traffic signal control interface.
2. Specific project activities will include:
1) Delivery of a smart city internet of things communication platform (LoRaWAN) for use by all for local authority devices for Slough and RBWM and as an open platform for commercial services and innovation. The aim is to provide over 90% coverage of population as is predicted for the existing deployment across the other four Berkshire authorities.
2) Actively promote commercial and start-up innovation on the smart cities platform through providing free access for at least the duration period of the project to the smart city communications platform.
3) Promote the smart city cluster and use the project momentum to develop and secure further funding opportunities.
3. You are recommended to give Thames Valley Berkshire Smart City Cluster project extension full financial approval in the sum of £283,620 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 below.
Other Implications
Financial
Item 7: BLTB 4 June 2020 Financial Approval TVB Smart City Cluster project extension 4. A call for bids process was undertaken in January 2020 and a list of prioritised projects were agreed at the BLTB meeting March 2020. See appendix 1. Thames Valley Berkshire Smart City Cluster project extension was given programme entry status at this meeting and funding for it was reallocated from Local Growth Funds to the Business Rates Retention Pilot (BRRP) monies.
5. This report recommends that Reading Borough Council be authorised to draw down the capital sum £283,620 from the Local Transport Body funding for this scheme.
6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
7. The risk management arrangements already put in place by the Local Transport Body are as follows: • The Assurance Frameworki has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes • Hatch Regeneris has been appointed as Independent Assessors and have provided a full written report (see Appendix 2) on the full business case for the scheme • The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
8. The scheme promoter is a local authority and they have to act within the law. Reading Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
9. The scheme will be carried out by Reading Borough Council.
10. The full details of the scheme are available from the Thames Valley Berkshire LEP websiteii. A summary of the key points is given below:
Task Timescale Procurement Via Reading Borough Council Contractor appointed Stantec Project start June 2020 Completion date Feb 2021
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Approval: Scheme 2.30 TVB Smart City Cluster extensionReport | 1.2 MB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.