CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Slough Borough Council
Berkshire Local Transport Body, Thursday 4 June 2020 at 4.00pm

Financial Approval 2.24 Newbury: Railway Station Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancements

Agreed Committee 1 paper

Berkshire Local Transport Body agreed this item on Thursday 4 June 2020. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

It was agreed that the demand analysis study be carried out before the date set out in condition 4 and that an update be provided to BLTB at the meeting on 15 th July 2020. At the conclusion of the discussion, financial approval was given to the Gate Line enhancements and Cycle Hub elements of the scheme, subject to the conditions set out in the report. In relation to the Office Space enhancements, it was agreed that the demand analysis study be carried out with an update to be provided to BLTB on 15 th July 2020 at which financial approval would be considered. Resolved – That scheme 2.24 Newbury: Railway Station Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancements be given conditional financial approval in the sum of £640,000 in 2020/21 on the terms of the funding agreement set out in paragraph 11 step 5 of the report and subject to final approval for the Office Space enhancements following completion of the demand analysis study to be provided to BLTB in July 2020; and the following conditions: Gate Line Enhancements 1. Provide confirmation of the operational design horizon for the proposed gateline capacity, based upon the projected local passenger growth forecast at the station, with a clear demonstration that this broadly aligns with assumptions made within the Economic Case and, if not, does not undermine the case for investment 2. GRIP 4 Network Rail Approval in Principle; and 3. An understanding of what processes would be undertaken in the event of any further cost overruns, should they arise. These conditions should be met at the earliest feasible date, but no later than 31st October 2020. Cycle Hub and Office Space enhancements 4. Completion of the demand analysis study, with a clear demonstration of strong potential demand for the business start-up units that correlates with a strong probability of high occupancy levels of the units; 5. GRIP 4 / GRIP 5 Network Rail Approval in Principle, as required for both the cycle hub and business start-up unit scheme element; 6. Evidence of completed commercial agreements between GWR and Network Rail for the necessary land transfer required to complete the business start-up units; and 7. Formal funding commitment from First Group and Network Rail for the match-funding identified by GWR, with a more detailed understanding of what processes would be undertaken in the event of any further cost overruns, should they arise. These conditions should be met at the earliest feasible date, but no later than 30th November 2020. The demand analysis study to be carried out more quickly with an update provided to BLTB in July 2020.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To consider giving financial approval to two enhancements to scheme 2.24 Newbury: Railway Station Improvements.

2. The original Newbury Railway Station Improvements scheme plans to enhance and improve multi-modal transport interchange at Newbury Railway station including upgrade and improvement of station buildings. This will work alongside, and help to deliver, the Market Street housing-led development and also help to deliver the Sandleford Park strategic housing site, through enhanced connectivity for bus passengers, rail passengers, cyclists and pedestrians. The scheme will allow Newbury Railway Station to cope with anticipated increases in passengers with corresponding increases in demand for travel and car parking. The scheme is promoted jointly by West Berkshire Council and Great Western Railway.

3. Since the original scheme was approved in July 2018, two enhancements have been proposed:

3.1Ticket Gate Line enhancements – refined future demand forecasts for Newbury and Network Rail safety requirements for passenger flows and clearance times, demonstrates that the number of gate lines originally proposed for the scheme is insufficient and is a critical safety issue.

3.2Cycle Hub and Office space enhancements – 180 spaces to be provided on the south-side of the station and 176 spaces on the north side, with some removal of platform provision to give a net addition of 300 cycle parking spaces at the station; and provision of 610m2 floorspace (an additional 44.5%) on the south side of the station for Business Start-up Units.

Recommendation

4. You are recommended to give scheme 2.24 Newbury: Railway Station Improvements financial approval for the two enhancements in the sum of

Item 9 BLTB 4 June 2020 Financial Approval 2.24 Newbury Railway Station: Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancements 4.1. £300,000 for Gate Line enhancements and

4.2£340,000 for Cycle Hub and Office Space enhancements

totalling £640,000 over the period 2020/21, on the terms of the funding agreement set out at paragraph 11 step 5 below, subject to the Independent Assessor being satisfied that the following conditions are met:

Gate Line Enhancements

4.3Provide confirmation of the operational design horizon for the proposed gateline capacity, based upon the projected local passenger growth forecast at the station, with a clear demonstration that this broadly aligns with assumptions made within the Economic Case and, if not, does not undermine the case for investment. 4.4. GRIP 4 Network Rail Approval in Principle; and 4.5. An understanding of what processes would be undertaken in the event of any further cost overruns, should they arise. These conditions should be met at the earliest feasible date, but no later than 31st October 2020.

Cycle Hub and Office Space enhancements

4.6Completion of the demand analysis study, with a clear demonstration of strong potential demand for the business start-up units that correlates with a strong probability of high occupancy levels of the units; 4.7. GRIP 4 / GRIP 5 Network Rail Approval in Principle, as required for both the cycle hub and business start-up unit scheme element; 4.8. Evidence of completed commercial agreements between GWR and Network Rail for the necessary land transfer required to complete the business start- up units; and 4.9. Formal funding commitment from First Group and Network Rail for the match- funding identified by GWR, with a more detailed understanding of what processes would be undertaken in the event of any further cost overruns, should they arise. These conditions should be met at the earliest feasible date, but no later than 30th November 2020.

Other Implications

Financial

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Approval 2.24 Newbury: Railway Station Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancementsAddendum 333 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 16 attended
RA
Councillor Robert AndersonCommittee Member, present
MB
Councillor Marc Brunel-Walker Bracknell Forest CouncilCommittee Member, present
GC
Councillor Gerry ClarkCommittee Member, present
PJ
Councillor Pauline JorgensenCommittee Member, present
TP
Councillor Tony Page Reading Borough CouncilChair, present
RS
Councillor Richard SomnerCommittee Member, present
SA
Stuart AtkinsonCommittee Member, present
CE
Charles EalesVice-Chair, present
MK
Malcolm KemptonCommittee Member, apologies
BM
Bob MountainCommittee Member, present
SR
Simon RatcliffeCommittee Member, apologies
MT
Matthew TaylorCommittee Member, apologies

All 16 on the meeting page

On this subject at Slough

Search all
  1. Financial Approval 2.24 Newbury: Railway Station Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancementsThis decision
  2. Financial Approval: Scheme 2.37 Bracknell A322/A329 Corridor Improvements: Birch Hill Junction UpgradeApproved
  3. Financial Approval 2.47 Bracknell: Town Centre - "The Deck"Approved
  4. Financial approval GBF1 Slough: Langley High Street Widening Phase 3Approved
  5. Financial approval: Scheme 2.45 Langley High Street Widening Phase 2Approved
  6. Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban RealmApproved

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies