Damp and Mould Update

Noted Executive 1 paper

AI summaryWaverley's Landlord Services Advisory Board noted a damp, mould and condensation report covering June to December 2025, which showed 280 cases, full compliance with Awaab's Law timescales and a 300% rise in workload.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedDamp and mould update received and noted
MoneyNot stated
What happens nextSystem triggers amended 1 March 2026Aim to reduce emergency mould treatments
Who it affectsCouncil housing tenantsAcross 4,823 property housing stock

What was decided

The board noted the Damp and Mould Scheduled Monitoring Analysis Report covering 1 June to 31 December 2025. Report P2

Why

The council has statutory duties under the Homes (Fitness for Human Habitation) Act, the Housing Regulation Act 2023, the Housing Health and Safety Rating System and Awaab's Law to protect tenants from damp and mould hazards. Report P4

The reporting period spans the introduction of Awaab's Law and the launch of the council's new Damp, Mould and Condensation Case Management System, both on 27 October 2025. Report P2, P20

A 300% increase in damp, mould and condensation work compared with the same period in 2024 has created significant pressure on limited resources. Report P27

What happens next

The case management system triggers will be amended from 1 March 2026 to reduce the number of emergency mould treatments, in line with findings and tenant feedback. Report P27

A specialist Damp, Mould and Condensation contractor is being procured; the tender was published w/c 26 January 2026. Report P9

Options for a tenant account with automated text updates will be discussed at the next system review meeting in April 2026, and the impact on inspector workload is being quantified. Report P8, P27

Options considered

  • Chosen: Note the report. Board satisfied with the compliance and performance information provided

Implications

  • Staffing: A 300% increase in DMC work compared with the same period in 2024 is described as having a significant impact on limited resources; inspector resourcing requirements are being quantified. Report P27
  • Legal: One disrepair claim relating specifically to damp and mould was active in the period, with a further seven claims making reference to damp and mould alongside other repairs; one Housing Ombudsman referral has produced no findings of maladministration to date. Report P25
  • Legal: No compensation payments have been made in relation to damp and mould cases during the period. Report P25
  • Equalities: 70% of cases between June and December 2025 involved a household with one or more identified vulnerabilities, including children under 16, residents over 65, and those with respiratory, mobility or immune-related conditions. Report P14
  • Climate: Environmental monitoring in six occupied properties is being used to identify early signs of condensation and inform investment decisions for similar properties across the stock. Report P18
  • Risk: Performance against Awaab's Law timescales was met for all inspections within 10 working days, but 16 cases exceeded the 24-hour statutory timescale, mostly because tenants requested later appointment dates. Report P23

Who and where

  • Council housing tenants across Waverley's 4,823 property housing stock Report P2, P23
  • Vulnerable tenants including children under 16, residents over 65, and those with respiratory, mobility or immune-related conditions Report P4, P14
  • Prospective tenants moving into void properties inspected for damp and mould risk Report P17

Timeline

  • 1 June 2025 to 31 December 2025: Reporting period covered by the damp and mould update Report P2
  • September 2025: Updated Damp, Mould and Condensation Policy adopted to reflect Awaab's Law duties enforceable from 27 October 2025 Report P4
  • 27 October 2025: Awaab's Law introduced and new Damp, Mould and Condensation Case Management System launched Report P2, P20
  • w/c 26 January 2026: Tender published for a specialist Damp, Mould and Condensation contractor Report P9
  • 1 March 2026: Case management system triggers to be amended to reduce emergency mould treatments Report P27
  • April 2026: Next system review meeting to consider tenant account functionality Report P8

Plain English for the jargon

  • Awaab's Law: Statutory requirements under the Social Housing (Regulation) Act 2023 that set binding timescales for landlords to address hazards such as damp and mould.
  • DMC: Damp, Mould and Condensation, used as shorthand for the council's case type and management system.
  • HHSRS Cat 1 hazard: A Category 1 hazard under the Housing Health and Safety Rating System, the most serious rating, where a hazard presents a serious and immediate risk to health.
  • DMC Case Management System: New system launched on 27 October 2025 to triage, track and audit damp, mould and condensation cases.
  • Void property: A council property that is empty between tenancies and is inspected and prepared before being re-let.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item103

Resolved

Resolved that: The Damp and Mould report be noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Landlord Services Advisory Board (Executive Working Group)

Report Title Damp and Mould Scheduled Monitoring Analysis Report Waverley Borough Council Information note to: Landlord Services Advisory Board Date: 26.02.2026 Author: Donovan Thompson Email: [email protected]

Summary This report sets out Waverley Borough Council’s management of damp, mould and condensation (DMC) across its housing stock for the period 1 June 2025 to 31 December 2025. It provides assurance that the Council is complying with the existing legislation and guidance, and that it is taking reasonable and proportionate steps to protect tenants from health-related harm caused by damp and mould. The reporting period is particularly significant as it spans the period before and after the introduction of Awaab’s Law on 27 October 2025 and the launch of the Council’s new Damp, Mould and Condensation Case Management System on the same date. This has allowed the Council to move from a predominantly reactive service to a regulated, time-bound and auditable statutory compliance framework.

1. Legislative and Policy Context

The Council has a statutory duty under the Homes (Fitness for Human Habitation) Act, the Housing Regulation Act 2023, the Housing Health and Safety Rating System and Awaab’s Law to ensure that tenants are not exposed to hazards that could cause harm. Damp and mould are recognised as serious health hazards, particularly for children, elderly residents and those with respiratory or immune-related conditions. During this period, Waverley Borough Council updated its Damp, Mould and Condensation Policy in September 2025 to reflect the statutory duties that became enforceable from 27 October 2025. The updated policy introduced legally binding timescales for inspections and repairs, strengthened requirements for communication with tenants, formal prioritisation of vulnerable households, explicit inclusion of void properties and preventative interventions within the Council’s damp and mould responsibilities. The policy now forms the operational basis for compliance with Awaab’s Law and underpins the Council’s inspection, diagnosis, repair and pro-active prevention activities.

2. Waverley Borough Council Approach, compliant with Awaab’s Law

Page 1 of 9 The tenant can report the issue via the website form or by calling Customer Services. If the tenant is familiar with technology, has internet access, the Customer Services Officer guides the tenant on how to report the case online. This is our preference of reporting as the tenant can add pictures, videos and any description they might want to add. The tenant is also advised that all communication and updates will be done via email. If the tenant is not comfortable with the online reporting or email communication, the form is filled out by the Customer Services Officer and communication is done via post and or telephone The system triages cases into Emergency and Significant categories. For Emergency cases, the response is as follows:  immediate order for 24 hours hazard removal of mould;  appoint inspection date for Inspector to attend within 10 working days;  Inspector raises further mould treatment order (if necessary) with a timescale for completion in 5 working days and/or prevention works with a timescale for completion of 20 working days. For Significant cases, the response is as following:  appoint inspection date for Inspector to attend within 10 working days;  Inspector raises mould treatment order with a timescale for completion of 5 working days and/or prevention works with a timescale for completion of 20 working days.

The tenant receives an automated letter at the following stages:  acknowledge report of issue;  confirmation of 24 hours mould wash appointment;  confirmation of inspection date and inspector name;  inspection summary report confirming findings and recommendation.  Further works stages are communicated by our contractor with updates added to our DMC Case Management System by us.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Damp and Mould UpdateReport 487 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 20 attended
PR
Councillor Paul RiversChair, present
TD
Terry DaubneyVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AL
Councillor Andrew LaughtonCommittee Member, present
JK
Councillor Jacquie KeenCommittee Member, present
AM
Councillor Alan MorrisonCommittee Member, present
JR
Councillor John RobiniCommittee Member, apologies
RB
Rod BlackmoreCommittee Member, present
RS
Robert StratfordCommittee Member, present
DW
Dave WilliamsObserver, expected
DM
Dave MaddamsObserver, present
AF
Alex FosterOfficer, present

All 20 on the meeting page

On this subject at Waverley

Search all
  1. Damp and Mould UpdateThis decision
  2. New contract for Damp, Mould and Condensation Prevention and Remediation ServicesDecided
  3. Damp and Mould Quarterly Update ReportNoted
  4. Damp and Mould Quarterly UpdateNoted
  5. Damp and Mould Quarterly Update (20 mins)Agreed
  6. Approval to commence tendering for Damp and Mould Specialist Services contractDecided

More from Waverley Landlord Services Advisory Board (Executive Working Group)

All decisions
MeetingDecisionOutcome
30 Jul 2026 Capital Programme updateRESOLVED that the Capital Programme update be noted. Noted Open
30 Jul 2026 Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... Noted Open
30 Jul 2026 Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. Noted Open
30 Jul 2026 Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. Noted Open
30 Jul 2026 Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. Noted Open