Waverley Borough Council

Water Remedial Actions Progress Report

Noted Executive 1 paper

AI summaryWaverley Borough Council's Landlord Services Advisory Board noted a progress report on water safety remedial works delivered by SMS Environmental Services Ltd, with 100% of planned maintenance completed since January 2026 and a clearer timeline expected by the end of February.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBoard received the water remedial progress report without further action
MoneyNot stated
What happens nextDetailed schedule by March 2026Clearer timeline expected by end of February 2026
Who it affectsCouncil housing tenantsResidents whose homes are receiving water safety works

What was decided

The board noted the Water Remedial Actions progress report.

Why

SMS has completed 100% of requested planned preventative maintenance since January 2026 while the additional contractor is being appointed. Report P4, P13

A preferred supplier for the additional water risk assessment and planned preventative maintenance contract was identified on 13 February 2026, with contractual discussions ongoing. Report P2

What happens next

WBC expects to receive confirmation of planned completion dates once the remaining actions are programmed into the Opuz system by the end of February 2026. Report P7, P11

More detailed targets and a fully agreed schedule for mitigating risks are expected by March 2026. Report P14

Implications

  • Risk: Two health and safety risks and two sites requiring immediate attention were identified during the interim arrangement, and SMS will prioritise new urgent risks. Report P5, P6
  • Risk: Three instances of non-access have been recorded, which could delay completion of remedial actions. Report P5
  • Other: Cost reductions were confirmed at one site after 47 flexi hoses were found not to require replacement. Report P13

Who and where

  • Council tenants in properties undergoing water safety remedial works Report P6
  • Waverley Borough Council landlord services Report P11

Timeline

  • 18 December 2025: SMS Environmental Services Ltd entered into a 36 month contract with WBC for water safety remedial actions Report P1
  • 22 January 2026: WBC met with SMS to review urgency and risks; all 609 actions uploaded to the Opuz portal Report P7
  • End of February 2026: All remaining remedial actions expected to be programmed into the Opuz system with a clearer timeline Report P7, P11
  • 9 February 2026: SMS began visiting all sites to assess required works and identify safety considerations Report P8
  • 13 February 2026: Preferred supplier for the additional WRA and PPM contract identified Report P2
  • By March 2026: More detailed targets and a fully agreed mitigation schedule expected Report P14

Plain English for the jargon

  • Opuz: SMS Environmental Services Ltd's portal system used to track water safety works and documentation
  • PPM: Planned Preventative Maintenance, the routine servicing tasks scheduled across housing sites
  • WRA: Water Risk Assessment, the process of identifying and evaluating water safety risks in properties
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item104

Resolved

Resolved that: The Water Remedial Actions progress report be noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Landlord Services Advisory Board (Executive Working Group)

Background

SMS Environmental Services Ltd (SMS) entered into a contract with WBC on 18 December 2025 to deliver all water safety remedial actions until full resolution is achieved. The contract is for 36 months, with the option to extend for a further 24 months.

A preferred supplier for the additional WRA and PPM contract was identified on Friday, 13 February 2026. Contractual discussions are ongoing to ensure that all obligations can be met before formally entering a 36-month contract, with the possibility of a 24-month extension.

3. Overview

Since January 2026, SMS has achieved 100% completion of all requested PPMs, while WBC continues progressing the appointment of the additional contractor. During this interim arrangement, the PPM process identified:

 3 instances of non-access  2 health and safety risks  2 sites requiring immediate attention

Page 1 of 2 SMS is aware of these issues and will continue to prioritise new urgent risks as they arise, taking necessary actions to mitigate them within safe and acceptable tolerances to ensure no harm to residents.

On 22 January 2026, WBC met with SMS to review the urgency and risks associated with outstanding remedial tasks. All 609 actions have now been uploaded to Opuz (SMS’s portal system) for planning and completion based on priority. Of these, 312 actions have scheduled assessment or completion dates, with the remainder expected to be programmed into the system by the end of February. Once finalised, WBC will receive confirmation of planned completion dates.

On 9 February 2026, SMS began visiting all sites to assess required works and to identify additional safety considerations such as access constraints, lighting, and asbestos-related issues. To date, 25 sites have been assessed to determine where specialist contractors may be needed and to ensure all safety factors are addressed before works commence.

4. Future Objectives

Although the contract has been in place for less than two months, including the Christmas period — SMS has demonstrated a strong and committed approach to addressing WBC’s water safety requirements.

WBC has reassurance of continuity and progress, as all works and documentation are being tracked via the Opuz system. A clearer timeline is expected by the end of February, at which point we aim to confirm when 100% of remedial actions will be fully resolved. WBC and SMS remain in daily communication due to the high volume of tasks requiring oversight.

To date, SMS has:

 Removed 5 duplicate remedial actions  Completed 100% of PPMs  Commenced surveying works  Confirmed cost reductions at one site due to 47 flexi hoses no longer requiring replacement  Appropriately prioritised tasks, with some risks downgraded following review

By March 2026, we expect to provide more detailed targets and a fully agreed schedule for mitigating risks and delivering required works, with a focus on eliminating as many risks as possible.

Page 2 of 2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Water Remedial Actions Progress ReportReport 130 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 20 attended
PR
Councillor Paul RiversChair, present
TD
Terry DaubneyVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AL
Councillor Andrew LaughtonCommittee Member, present
JK
Councillor Jacquie KeenCommittee Member, present
AM
Councillor Alan MorrisonCommittee Member, present
JR
Councillor John RobiniCommittee Member, apologies
RB
Rod BlackmoreCommittee Member, present
RS
Robert StratfordCommittee Member, present
DW
Dave WilliamsObserver, expected
DM
Dave MaddamsObserver, present
AF
Alex FosterOfficer, present

All 20 on the meeting page

On this subject at Waverley

Search all
  1. Water Remedial Actions Progress ReportThis decision
  2. Water Remedial Actions Progress ReportNoted
  3. Water Remedial Actions Progress ReportNoted
  4. Water Remedial Actions Progress ReportNoted
  5. New Contract for Water Hygiene Remedial WorksApproved

More from Waverley Landlord Services Advisory Board (Executive Working Group)

All decisions
MeetingDecisionOutcome
30 Jul 2026 Capital Programme updateRESOLVED that the Capital Programme update be noted. Noted Open
30 Jul 2026 Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... Noted Open
30 Jul 2026 Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. Noted Open
30 Jul 2026 Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. Noted Open