Resolved
Decision Noted the update on the progress of the project
Helensburgh CHORD Project Board noted this item on Tuesday 23 March 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Noted the update on the progress of the project
Resource Allocation Schedule HH02 - Helensburgh - Redevelopment of the West Bay Esplanade
£ Cost £ Cost to Internal/ Input FBC Input completion Reference Activity Start Date End Date Resource External Days 28/1/2011 Days Jan 2013 Management of the HH02_RA001 project Jun-09 Jan-13 Project Manager External 96 30,000 194 60,000 Project Team HH02_RA002 Arrange meetings etc Jun-09 Jan-13 Administrator Internal 18 No cost 42 No cost
HH02_RA003 Financial advice/support Jun-09 Jan-13 Strategic Finance Officer Internal 18 No cost 42 No cost HH02_RA004 Legal advice Jun-09 Jan-11 Lawyer Internal 2 500 4 1,000 HH02_RA005 Planning advice Jun-09 Jan-11 Planner Internal 6 No cost 12 No cost HH02_RA006 Roads/Traffic advice Jun-09 Jan-13 Road/Traffic Engineer Internal 10 No cost 22 No cost HH01_RA007 Project Design Dec-09 Jan-13 Design Team - External n/a lump sum £89,358 n/a lump 147,588 Landscape sum Architect;Traffic Mgt Engineer;Strucutal/Civil Engineer; Urban Designer etc HH01_RA008 Project Costing Dec-09 Jan-13 Quantity Surveyor External n/a lump sum £7,700 n/a lump 33,075 sum HH01 RA009 CDMC Jan-09 Jan-13 CDMC External n/a lump sum £4,500 n/a lump 9,000 sum HH01_RA011 Site Investigations March May-10 Engineer External n/a lump sum £8,500 n/a lump 8,500 sum HH01_RA012 Topographical survey Feb-10 Apr-10 Engineer External n/a lump sum £993 n/a lump 995 sum HH01_RA013 Consultation Costs Feb-10 Jun-10 n/a n/a n/a lump sum £1,850 n/a lump 1,850 sum Totals £143,401 £262,008
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
5HH02 Resource Schedule V1 3Report | 42 KB | DownloadRead as text |
PDF |
6Helensburgh CHORD Esplanade Risk Register HH02 v1 3Report | 93 KB | Download |
PDF |
8CHORD WEST BAY PROJECT PROGReport | 27 KB | Download |
PDF |
Highlight/Progress Report HH02- Rejuvenating the West Bay EsplanadeReport | 78 KB | Download |
Follow Helensburgh CHORD Project Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Feb 2012 | Highlight/Progress ReportDecision Noted the update on the progress of the Highlight/Progress Report. (Ref: Report by CHORD Project Manager, da... | Noted | Open |
| 9 Feb 2012 | Helensburgh Chord Risk RegisterDecision Noted the update on the current progress of Risk Register. (Ref: Report by CHORD Project Manager, dated 1 Fe... | Noted | Open |
| 9 Feb 2012 | Project PlanDecision Agreed to note the update by the CHORD Design Team. Agreed that updates will be provided, to the Board at th... | Agreed | Open |
| 5 Apr 2011 | Highlight progress reportDecision To note the update on the progress of the Highlight/Progress Report. | Noted | Open |
| 5 Apr 2011 | Helensburgh chord risk registerDecision To note the update on the progress of the Risk Register. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.