AI summaryArgyll and Bute Council's Environment, Development and Infrastructure Committee noted cemetery sales and site progress, with a revised £635k five year programme budget [D] [P45]. Work to secure land and progress cemetery extensions will continue as planning and survey requirements are met [P44] [P40].
Written from the decision and the officer reportPDF Pro
OutcomeNoted224 lairs sold; 12,728 spaces remain available [P31]
Money£635k five year budget [P45]Existing capital budget covers the current estimate [5.3]
What happens nextContinue priority site programme [P44]Secure land and progress sites as approvals allow [P40]
Who it affectsServices at 63 active cemeteries [P31]Local availability varies; 24 sites restrict lair sales [1.3] [P36]
What was decided
The committee noted annual lair sales figures and the remaining availability of lairs. Report 1.1
It noted updated comments on the Cemetery Development programme. Report 2.2
It noted progress on selecting sites and obtaining approval for new or extended cemeteries. Report P44
Why
The portfolio has 131 cemetery locations. The 63 active cemeteries have 12,728 lairs available, enough overall for the next 50 years. Report 1.1, P31, 5.1
Lair sales differ from burials because each lair can usually accept two or three interments. Local pressure remains, with sales restricted at 24 active sites. Report 1.2, 4.2, P32, P36
Groundwater rules, land negotiations, planning conditions and required surveys can delay delivery. Report 1.4, P40, P42
What happens next
The 2026 programme will continue within the priority list, maximise lair space and restrict sales where needed. Report P43, P44
For Kilkerran North, the Council will pursue land transfer, design and a planning application, while investigating deeper lairs at Achnabreac. Report P46
Island programme work includes Calgary, Pennygowan, Salen, Tobermory, Sorobay and Pennyfuir. Other work includes Strachur, Cowal, Kilmun, Kingarth and Cnoc an Rear, while Arrochar is a potential extension. Report P47, P48, P49
The money
£635k Revised five year cemetery development budget Report P45, 5.3
£688k Capital Environmental Projects Budget available for the programme Report 1.5
£250k Kilkerran North cemetery extension estimate Report P46
£150k Cowal Sandbank extension development estimate Report P48
£75k New cemetery site search south of Strachur Report P48
£50k Achnabreac and Kingarth development estimates Report P46, P48
£30k North Bute addition and Calgary extension estimates Report 1.4, P47
£605k Original five year programme budget requirement Report 1.4
Options considered
Chosen: Continue the priority cemetery development programme. Suitable land must be identified and confirmed before locations can be obtained. Report P44
Chosen: Maximise lair space and restrict lair sales. These measures preserve burial services at as many active cemeteries as practicable. Report P44
Chosen: Develop extensions or new cemetery sites. Local pressure on lair availability requires added capacity. Report P32, P44
Rejected: Balliemeanoch and Glen Sluain for a Strachur cemetery. The areas were essential productive agricultural land and unavailable for a cemetery. Report P38
Rejected: Loch Fyne side of Strachur. The topography prevents development. Report P38
Rejected: Second Kingarth Parish Church footprint. Shallow substructures make development impracticable. Report P10, P40
Rejected: Full archaeological investigation of the initial Calgary extension. It would be excessively expensive and compromise the unit rate for new lair space. Report P42
Implications
Financial: The revised £635k estimate remains within the Capital Environmental Projects Budget, so no extra budget line is required at this time. Report P45, 5.3
Legal: The Council must keep at least one cemetery available because it is the Burial Authority. Report 6.3
Legal: Lair sales can be restricted where capacity is under 10 years, and restrictions apply at 24 sites under section 3 of the updated Cemetery Management Rules. Report 6.1, P36
Risk: Land suitability, availability and development costs may affect whether local burial services can be retained. Report 6.6
Risk: Archaeological finds may restrict the Calgary extension, while the lack of a written land commitment may limit Kilkerran development. Report P6, P39
Other: The programme aims to maintain burial services locally wherever practicable and retain an active cemetery on main inhabited islands wherever practicable. Report 6.5, 6.11
Other: Local burial services support Council and private provider business models and reduce costs for customers. Report 6.10
Other: No staffing, climate change, Fairer Scotland Duty, equalities or rights of the child implications are known. Report 6.4, 6.8, 6.9, 6.12
Who and where
People using the Council's burial service Report 1.1, 6.3
Communities served by 24 sites with lair sales restrictions Report 2.3, P36
Customers of the Council and private burial providers Report 6.10
Timeline
30th September 2025: The report's lair, availability and programme data were collated to this date. Report 1.1
November: Further Calgary ground investigations and Kingarth archaeological survey work were scheduled. Report P6, P10
late November to early December: Kilkerran archaeological trenches were scheduled after grazing ended. Report P38
early in 2026: The Council will contact the Community Council and landowners to review Strachur options. Report P38
2026: The priority programme continues, and Cowal design work and a planning application are scheduled. Report P40, P43
2026 to 2027: Cowal extension development is targeted. Report P48
2027: Kingarth phase 2 extension development is targeted. Report P48
2027 to 2028: Kilkerran North phase 1 completion is targeted. Report P46
Plain English for the jargon
Lair: A burial space for which someone can obtain the exclusive right of burial through a lair certificate [4.1].
Active cemetery: A cemetery where land remains available and a lair space can be allocated [P30].
Closed cemetery: A cemetery where all available burial land has been allocated, although reopening and ashes interments remain possible [P30].
Lair sales restriction: A limit on selling lairs because of low remaining capacity or a need to preserve local burial facilities [2.3] [P36].
Interment: A coffin or ashes burial recorded in the cemetery statistics [4.4] [P27].
Maximise lair space: Bringing ground into burial use, including former hard or soft landscaped areas [P31].
Cemetery Development programme: The priority programme for extensions and new cemetery sites, supported by maximising lair space and sales restrictions where needed [P44].
SEPA: The body involved in site advice and groundwater management requirements for cemetery development [1.4] [P40].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
Decision The Environment, Development and Infrastructure Committee noted: 1. the annual lairs sales figures and remaining availability; 2. the updated comments relevant to the Cemetery Development programme; and 3. the progress on site selection and approval for development of new or extended cemeteries within the priority programme. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services, dated December 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee, 11 pages
Executive summary
1.1Within the cemetery inventory of 131 locations, 63 cemeteries remain “active” with lairs spaces available. This report provides the annual update on the current Argyll and Bute “active” cemetery portfolio - numbers available for sale of lair certificates and operational timescales within the Cemetery Development programme, based on data collated to 30th September 2025.
1.2It should be noted that the rate of sale of lairs, equivalent to the uptake of land, differs from the annual rate of interments (coffin burials) as generally, individual lairs are able to accept 2 or 3 interments.
1.3Figures collated after a comprehensive lair survey in 2024 have been updated this year to indicate that there remains over 12,700 lairs available for sale throughout our cemetery inventory, sufficient to sustain the burial service overall, for the next 50 years. However, the number of lairs available varies from several hundred in larger cemeteries to 10 or less, depending on the location. These figures are used to prioritise the cemetery development programme of existing extensions or new cemetery development sites.
1.4The timescales from planning an extension to an existing or providing a new cemetery, through to operational availability varies depending on the complexity of each project. SEPA ground water management requirements, which have become far more stringent over the past decades, local consultations with landowners on the transfer of ownership and the Planning approval process all contribute to the length of time taken to deliver new cemetery lairs. Further planning conditions require Soils Management Plans and Ecology and Archaeology surveys of any potential plot of land. For this reason, the current priority list highlights development needs in 0-5yrs, 5- 10yrs or 10-20yrs. The 5-year development programme budget requirement remains at £605k. However, an additional £30k development costs for North Bute cemetery have been added in anticipation of an early spend, within the programme period.
1.5Activities in the past 12 months have been limited to ground investigation works. Construction plans for additional lairs space have yet to be approved. There is a total of £688k in the Capital Environmental Projects Budget which will cover this cost of £605k-£635k as per Appendix 2 for the next 5 years. 1.6 Discussions with landowners and community groups continue, on potential cemetery locations, in association with initial site investigation trial pit excavations to verify the suitability of land for cemetery development.
• A formal planning application has been approved for Calgary Cemetery extension, with conditions. This required additional ground investigation works which initially uncovered archaeological finds which may restrict the extent of development. Further investigations are scheduled for November to confirm. In parallel with this, arrangements are underway with the landowner to transfer ownership of the selected section of field to the Council.
• At Cowal Cemetery - Sandbank trial excavations in adjacent Torlochan extension site, carried out last July were followed up with Ecology and Archaeology surveys this summer. The site is considered suitable for development as a cemetery. A formal planning application will be submitted towards gaining approval to develop within the 5 year programme duration, phase one of the extension providing an additional 200 lairs or thereby.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.