REST AND BE THANKFUL ROUNDTABLE DISCUSSIONS REPORT
NotedCommittee3 papers
AI summaryArgyll and Bute Council's Environment, Development and Infrastructure Committee noted local stakeholder concerns about the A83 [D] [2.1]. The Cabinet Secretary instructed Transport Scotland to review work on two way medium term operation, including the forestry track and a full two way road [D] [3.1].
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet Secretary instructed Transport Scotland to review the options [D]
MoneyNot stated
What happens nextNot stated
Who it affectsA83 traffic and local businesses [1.8] [4.1]Closures caused disruption and diversions, while measures affected businesses [1.2] [1.8]
What was decided
The committee noted the report and the concerns raised by local stakeholders.
It noted that the concerns were summarised in a letter to the Cabinet Secretary for Transport, attached at Appendix 1. Report 3.1
It noted that the response attached at Appendix 2 acknowledged economic and wellbeing concerns. It also noted that the Cabinet Secretary had instructed Transport Scotland to review two way medium term operation, including the forestry track and a full two way road option. Report 3.1
Why
The response acknowledged economic and wellbeing concerns.
Landslides continue regularly despite mitigation, including closures after heavy rain and debris flows of hundreds of tonnes. Report 1.5
Local businesses in Argyll and Bute have been adversely affected by the measures taken forward. Report 1.8
What happens next
Transport Scotland will review work undertaken so far on two way operation for the medium term solution. The review includes the forestry track and a full two way road option. Report 3.1
Medium term measures include improving the Old Military Road, managing landslide risk and connecting proposed works to the B828. Report 4.1
The preferred long term solution is a 1.4 km debris flow shelter along the existing A83. Construction is estimated to take three to four years after improvements to the Old Military Road. Report 4.1
Options considered
Chosen: Review work on two way operation for the medium term solution. The review covers the forestry track and a full two way road option. Report 3.1
Implications
Financial: The Cabinet Secretary acknowledged economic concerns raised by local stakeholders.
Risk: Landslides continue regularly despite mitigation, with closures after heavy rain and debris flows of hundreds of tonnes. Report 1.5
Climate: More intense rainfall is increasing the frequency and intensity of landslips. Report 1.5
Risk: During A83 closures, short term measures include a diversion, convoys and temporary traffic lights. They also include debris fences, catch pits, drainage and daily monitoring. Report 4.1
Legal: An Environmental Impact Assessment was published in December 2024, and statutory consultation ended February 7, 2025. Report 4.1
Legal: Draft Road Orders went out for engagement at the end of 2024 as part of consultation. Report 4.1
Risk: Construction of the proposed debris flow shelter is estimated to take three to four years after Old Military Road improvements. Report 4.1
Other: The long term proposal includes car park and viewpoint upgrades and a new active travel link. Report 4.1
People who may use the new active travel link Report 4.1
Local stakeholders
Timeline
October 2007 and September 2009: The first widely reported closures followed heavy rain and caused disruption and long diversions. Report 1.2
August and September 2020: Two unprecedented landslides deposited 6,000 and 10,000 tonnes on the road. Report 1.4
December 2024: The Environmental Impact Assessment was published. Report 4.1
at the end of 2024: Draft Road Orders were sent out for engagement. Report 4.1
February 7, 2025: The statutory consultation period for the Environmental Impact Assessment ended. Report 4.1
6 November 2025: The officer report was dated and submitted for committee consideration. Report P15
2023, 2024, and 2025: Notable landslides included closures after heavy rain and debris flows of hundreds of tonnes. Report 1.5
18 December 2025: The committee considered the report. Report P9
Plain English for the jargon
A83: Road affected by recurring landslips at Rest and Be Thankful [1.1].
Rest and Be Thankful: Location of recurring landslips on the A83 [1.1].
MTS: Medium term solution for two way operation [3.1].
OMR: The Old Military Road, used as a diversion [4.1].
EIA: Environmental Impact Assessment [4.1].
Debris flow shelter: Preferred 1.4 km long term solution on the existing A83 [4.1].
Convoy system: Traffic management for the Old Military Road diversion [4.1].
Road Orders: Draft orders sent for engagement during road consultation [4.1].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
Decision The Environment, Development and Infrastructure Committee: 1. noted the contents of the report and the concerns raised by local stakeholders; and 2. noted that: i. the concerns had been summarised in a letter to the Cabinet Secretary for Transport, attached at Appendix 1 of the submitted report; ii. a response had been received from the Cabinet Secretary for Transport acknowledging the economic and wellbeing concerns, attached at Appendix 2 of the submitted report, and; iii. the Cabinet Secretary for Transport had instructed Transport Scotland to review the work undertaken to date in relation to providing two-way operation for the medium term solution including use of the forestry track and a full two-way road option. (Reference: Report by Executive Director with responsibility for Development and Infrastructure, dated 6 November 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee, 8 pages
Executive summary
1.1Landslips on the A83 at the Rest and Be Thankful have been a recurring issue for decades. They became a major and persistent problem in the mid-2000s
1.2The first widely reported closures occurred in October 2007 and September 2009, following heavy rain, caused significant disruption and long diversions. These events highlighted the vulnerability of the route to debris flows and slope instability.
1.3Since 2010, landslides have occurred more frequently and with greater impact, prompting Transport Scotland to invest in mitigation measures such as debris fences and catch pits.
1.4Two unprecedented landslides in August and September 2020 deposited 6,000 and 10,000 tonnes of material on the road, leading to prolonged closures and accelerating plans for a long-term solution (including a proposed debris flow shelter).
1.5Despite mitigation, landslips continue regularly, with notable incidents in 2023, 2024, and 2025, including closures after heavy rainfall and debris flows of hundreds of tonnes. The frequency and intensity have increased due to climate- related factors like more intense rainfall.
1.6In summary: Landslips have affected the A83 for at least 20 years, but the problem has become critical since 2007 and particularly severe since 2020. 1.7 The Scottish Government is in the process of reviewing short, medium and long term plans for the Rest and Be Thankful. This report gives details on the solutions being presented as well as local concerns raised via a Round Table Group sanctioned by the Transport Secretary for Transport Fiona Hyslop and Chaired by Jenni Minto MSP.
1.8Currently there are three stages being taken forward by Transport Scotland as mitigation measures for the issues being experienced at the Rest and be Thankful for many years which have adversely affected local businesses in Argyll and Bute. Short, Medium and Long-term measures are presented at a high level in this report.
1.9A summary of the Roundtable discussions is further reported. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE SERVICES 18 DECEMBER 2025
REST AND BE THANKFUL ROUNDTABLE DISCUSSIONS REPORT
2.0INTRODUCTION
2.1This report advises of the current and planned measures to mitigate against the closures and works to the A83 Rest and Be Thankful by the Scottish Government as well as updating the committee on the Roundtable stakeholder discussions chaired by Jenni Minto MSP.
Recommendations
3.1It is recommended that members of the EDI Committee a. consider the contents of this report and the concerns raised by local stakeholders. b. Note that i. these concerns have been summarised in a letter to the Cabinet Secretary for Transport (Appendix 1) ii. a response has been received from the Cabinet Secretary for Transport (Appendix 2) acknowledging the economic and wellbeing concerns and that iii. the Cabinet Secretary for Transport has instructed Transport Scotland to review the work undertaken to date in relation to providing two-way operation for the MTS including use of the forestry track and a full two way road option. 4.0 DETAIL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.