What was decided
Cabinet approved objectives for Convent Way Estate redevelopment and the recommended delivery option: whole estate redevelopment through a contractual development partnership. Report P43, P52
Cabinet allocated up to £1.68m from the HRA Council House Building capital programme contingency for technical advisors and consultant services to procure a development partner. Report 6.2, 12.1
Cabinet approved in-principle use of compulsory purchase powers to secure vacant possession, the commencement of developer partner procurement, and the Engagement Strategy. Report P58, P63
Why
The 1960s Wimpey No Fines blocks are described as among the poorest in the borough, with cracked walls, corroded ties, damp ingress, failing roofs, low thermal performance and most homes at EPC D, with ongoing compliance and maintenance costs estimated at around £2.3m per year. Report P18, P19, P20, P21
An estate-wide redevelopment was assessed as the highest-scoring option because retaining and refurbishing the blocks carries large and escalating 30-year costs and fails to address long-term structural issues, while partial redevelopment is unlikely to be viable. Report P81, P83
A 2021 resident ballot showed 80% of voting households in favour on an 85% turnout, building on prior consultation, and the regeneration is aligned with the Council's Housing Strategy 2025-2030, Corporate Plan, and Climate Emergency Action Plan. Report P14, P27, P8, P30
What happens next
Officers will run a Competitive Flexible Procedure tender, starting with a Find a Tender Service notice in Q2 2026/27, developer bid final submissions in Q2 2027/28, and a future Cabinet decision to appoint the partner in Q3/Q4 2027/28 alongside a Full Business Case. Report P54, P86, P165, P166, P167, 6.3
A hybrid planning application is expected in Q4 2027/28, with any compulsory purchase order pursued in 2029/30, and Initial Demolition Notices to be issued in the months after the Cabinet decision. Report P168, P169, P60, P61
An Equalities Impact Assessment, Climate Change Impact Assessment, leaseholder and tenant re-engagement, and Resident Forum re-establishment will run in parallel under the approved Engagement Strategy. Report P63, P68, 8.7, 9.7, P56
The money
- £1.68m Procurement stage budget for technical advisors and consultant services, funded from the HRA Council House Building capital programme contingency Report 6.2, 12.1
- around £2.3m per annum Current estimated annual cost of compliance, repairs and maintenance on the existing estate Report P21
- £3m HRA savings programme Approved in February 2026, delivery required in 2026/27 and 2027/28 as a condition of the scheme proceeding Report P176
Options considered
- Chosen: Option 3: Redevelopment of the whole estate via a Contractual Partnership. Highest scoring on objectives; most cost-effective over 30 years; delivers the Landlord Offer; partial redevelopment ruled out as unlikely to be viable Report P46, P52, P81
- Rejected: Option 1: Maintain minimum regulatory quality and safety standards. Escalating costs and fails to address long-term structural issues Report P44, P83
- Rejected: Option 2: Capital or major works refurbishment. Substantial 30-year revenue and capital costs without resolving structural issues Report P45, P81, P83
- Rejected: Option 4: Partial redevelopment of the estate. Unlikely to be viable; the Master Development Agreement would still allow later phases to be omitted if needed Report P47, P81
- Rejected: Self-delivery by the Council. Uncertainty around deliverability, financial risk to the Council, and no mechanism to deliver private sale homes needed for viability Report P83
- Rejected: Open procurement procedure. Does not allow negotiation or dialogue needed for a long-term, high-value scheme Report P85
- Rejected: Direct award of development partner. Not appropriate for a project of this size, complexity and value Report P85
Implications
- Financial: The £1.68m is funded from the HRA contingency; the wider scheme is expected to require a substantial share of additional HRA borrowing headroom over the next 4 years and depends on GLA grant funding at modelled levels. Report 12.1, 12.2, P99, 10.5
- Legal: The Council will rely on its compulsory purchase powers, Housing Act 2004 demolition notice procedures, S20 Landlord and Tenant Act 1985 consultation, and the Procurement Act 2023, with a future Cabinet report needed to make any CPO. Report 7.2, 7.3, 7.4, 7.5, P58
- Equalities: Cabinet must have due regard to the public sector equality duty under S149 Equality Act 2010; a full EQIA will be developed with the Full Business Case, and all new homes will be to Lifetime Homes standards with 10% to Wheelchair Standards. Report 7.6, 8.5, 8.7
- Climate: The scheme supports the Climate Emergency Action Plan 2026-2030 priorities on wider borough emissions and climate resilience, and is expected to explore AECB standards, heat pumps, SuDS and green infrastructure. Report 9.1, 9.2, 9.4, 9.5
- Risk: Key risks include deliverability within the HRA Business Plan, uncertainty over GLA funding, leaseholder buyback costs, land assembly delays, planning risk, procurement failure, and construction cost inflation. Report P98, P99, P100, P101, P102, P103, P104, P107
- Staffing: A dedicated programme team and expert technical, commercial and legal advisors will support the procurement and delivery phases. Report P104, 6.2
Who and where
- Around 250 council tenant households on the Convent Way Estate Report P4, P14
- 140 leaseholder households on the estate Report P4, P56, P100
- Six ground floor commercial unit occupiers Report P4, P56
- Over 4,200 households on the council housing register Report P25
- The wider Heston West, East and Central area community Report P23, 8.3
Timeline
- January 2020: Cabinet approved the Estate Regeneration Programme covering Convent Way (CEX432) Report P1, P188
- July 2021: Cabinet approved further progression of Convent Way regeneration after an 80% ballot in favour (CEX543) Report P2, P14, P189
- Q2 2026/27: Indicative date for issuing the Find a Tender Service notice, subject to Cabinet approval Report P165
- Q2 2027/28: Final developer bid submissions Report P166
- Q3/Q4 2027/28: Cabinet decision to award the development partner contract, subject to Full Business Case Report P167
- Q4 2027/28: Hybrid planning application expected to be submitted Report P168
- 2029/30: Indicative date for any Compulsory Purchase Order, subject to further Cabinet approval Report P169
Plain English for the jargon
- Contractual Partnership: A development partnership model with joint governance but no separate legal entity, allowing the council to retain control over key decisions
- Competitive Flexible Procedure (CFP): A procurement route under the Procurement Act 2023 allowing a multi-stage competitive tender with structured dialogue
- HRA (Housing Revenue Account): The ring-fenced account that holds rental income and expenditure for council housing
- Initial Demolition Notice (IDN): A notice under the Housing Act 2004 that suspends the council's duty to complete Right to Buy applications
- Compulsory Purchase Order (CPO): A legal mechanism allowing the council to acquire land, including leasehold interests, against the owner's will, subject to compensation
- Wimpey No Fines: A 1960s construction method using concrete without fine aggregate, associated with widespread structural defects
- Lifetime Homes and Wheelchair Standards: Design standards for accessible and adaptable housing