Update on progress of SEND and AP (Alternative Provision) Programme and Safety Valve
NotedExecutive1 paper
AI summaryHounslow Cabinet extends SEND and AP Programme to end of October 2026, spending the remaining £333k of its budget before handing the work over to Business as Usual as the national Safety Valve scheme closes.
Written from the decision and the officer reportPDF Pro
OutcomeNotedProgramme moves to Business as Usual in October 2026
Money£333k remaining budgetUsed to fund the seven month extension
What happens nextSEND Reform Plan by June 2026Required after national Safety Valve closure on 1 April 2026
Who it affectsChildren and young people with SENDAnd their families across the London Borough of Hounslow
What was decided
Cabinet noted delivery to date by the programme since the Strategic Business Case was approved in December 2023. Report P2
Cabinet approved extending the programme to the end of October 2026, to deliver a thematic approach to inclusion that feeds into the SEND Reform Plan due in June 2026, using the remaining £333k of programme budget. Report P3
Cabinet agreed that the programme's work will transition to Business as Usual in October 2026. Report P4
Why
The 2024 Ofsted and CQC inspection gave an improved middle rating, the Written Statement of Action was closed in December 2024 with 99% of milestones complete, and the SEND cohort educated in mainstream rose from a 28% baseline to 34% in Autumn term 2025, above the original Safety Valve target. Report 2.6, P70, 2.7, P17
The national Safety Valve Programme was announced on 9 February 2026 as closing on 1 April 2026, to be replaced by wider DSG deficit arrangements and a local SEND Reform Plan, and a White Paper on SEND reforms was released at the end of February 2026. Report 2.9, 3.6, P90
What happens next
Between April and October 2026, the extended programme will focus on five themes: Commissioning for Inclusion, Resources for Inclusion, Practice for Inclusion, Safety Valve monitoring, and the SEND Reform Plan. Report 5.1, P73, P74, P75, P76, P77
Several existing projects, including Local Offer, Alternative Provision, Children's Therapies, Preparation for Adulthood, the SEND Operating Model and Re-profiling Provision, are being handed over to Business as Usual by March 2026, while Resource Pathways and Top up Funding continue under the extension. Report 2.5, P51, P55, P57, P58, P60, P61, P63
A SEND Reform Plan must be written by June 2026 in response to the White Paper, with the next full area SEND and AP inspection expected within approximately three years of the October 2024 inspection. Report 2.6, 2.9, 3.6, P70
The money
£333k Remaining programme delivery budget to fund the extension to October 2026 Report P3, P116, P119
£2,169k Total approved revenue for programme delivery across its life Report P21, P116
£5,050k Approved revenue for SEND operational capacity, of which £1.6m per year for 2024/25 to 2026/27 plus £250k for the Independent Futures team Report P22, P126
£6,365k Approved capital budget, of which £33k spent on two Lindon Bennett feasibility studies that concluded the expansion was not feasible Report P23, P130, P131, P132
£13.6m Total programme investment, combining programme delivery, operational capacity and capital Report P156
£47.2m Cumulative deficit forecast under the do-nothing model at 31 March 2026 Report 2.8, P89, P162
£11.8m Forecast cumulative deficit at 31 March 2026 at Q3 following programme interventions Report 2.8, P89, P162
£84.4k Cost avoidance achieved through the first phase of the Independence and Employability Hubs Report P61
£329k Spend reduction by April 2025 from 8 Independent Futures interventions, against an original projection of £243k Report P98, P102
£853k Anticipated cumulative full year placement cost avoidance, exceeding the 2026/27 projection Report P98, P102
£1.6m Original cumulative SEN Transport saving target over the Safety Valve period, now superseded Report P93
£1m Revised SEN Transport saving target under the One Hounslow Financial Strategy for 2026/27 to 2027/28 Report P94
£300k Projected 2027/28 cost reduction in transport expected to support a moderate reduction in carbon emissions Report 11.3
Options considered
Chosen: Extend the SEND and AP Programme to end of October 2026 with a thematic approach using the remaining £333k of programme budget. A number of areas still require a programme management approach to deliver Safety Valve interventions, the SEND Reform Plan, and the move to Business as Usual Report P3, 5.1, P73, P74, P75, P76, P77
Rejected: Expand the Lindon Bennett Main Street site to add special school places. Two feasibility studies concluded the options were not feasible, with challenges that could not be mitigated and a low return on investment Report P23, P130, P131, P166
Rejected: Achieve a £615k annual net saving on high-cost residential placements through the Independent Futures team. Original savings figure could not be achieved in the desired timescales due to recruitment difficulties and the number of young people who can be moved from high-cost placement, although interventions have still delivered £329k and a projected £853k cumulative Report P97, P98
Implications
Financial: Programme is forecast to deliver within the £2,169k revenue budget, with £333k of the £2,165k total released for the seven month extension. Report P3, P21, P116, P120
Financial: Operational capacity budget of £5,050k is being subsumed into the wider Lifelong Learning, Skills and Employment Directorate restructure, with the new service modelled at £1.8m from 2026/27. Report P22, P125, P127
Financial: Allocated capital of £6,365k for Lindon Bennett is anticipated to form part of borough wide plans for special schools, after feasibility studies concluded the expansion was not viable. Report P23, P131, P132, P167
Financial: Safety Valve forecast at December 2025 shows a small in-year overspend of £0.1m (0.18%) for 2025/26, expected to be recovered by year-end through planned mitigations. Report P87
Legal: The Council has statutory duties under Section 19 of the Education Act 1996 and Section 42 of the Children and Families Act 2014 to secure suitable education and SEND provision, and the Public Sector Equality duty under Section 149 of the Equality Act 2010 is being applied across the programme. Report 9.1, 9.2, 10.2
Equalities: The programme is designed to broaden support in mainstream education and improve pathways for young people with SEND; an overarching Equalities Impact Assessment has not been prepared, with EQIAs done at project level instead. Report 10.1, 10.3
Climate: Limited direct climate implications, but more locally provided inclusive facilities and SEND transport routing software are expected to reduce out of borough journeys and produce a moderate carbon reduction, alongside a projected £300k transport cost reduction in 2027/28. Report 11.1, 11.2, 11.3
Risk: Two programme risks are scored at 9: unit cost inflation in placements due to market conditions, and wider external inflationary pressures on the High-Needs Block, with mitigations including a Market Management Strategy, brokerage strengthening, DfE liaison and on-going financial monitoring. Report 7.1, P107, P109
Staffing: The SEND Operating Model work has been superseded by the wider LLSE restructure, with SEND staffing steady at 30 FTE for 9 to 12 months, rising to a temporary 36 FTE in January 2026, and a permanent structure being developed. Report 12.1, P63, P125, P152
Who and where
Children and young people with SEND in the London Borough of Hounslow and their families Report P44, 10.1
Mainstream schools in Hounslow, with the Mainstream Inclusion Partnership supporting 934 children across 72% of schools and SENIF covering over 5,800 children in 2025/26 Report P14, P52
SEND service staff, with the programme moving to a permanent staffing structure and agency proportion steady at around 50% in 2025 Report P63, P125
Post 16 young people with SEND, served by the new Independence and Employability Hubs Report P55, P61
Parents and carers, engaged through the Parent Carer Forum, SENDIASS, monthly SEND Surgeries and Partnership Summits Report P51, P66, P67
Timeline
December 2023: Cabinet approved the Strategic Business Case for the SEND and AP Programme Report 2.3, P28
October 2024: Ofsted and CQC SEND and AP Inspection took place with an improved middle rating Report 2.6, P27
Within approximately three years of October 2024: Next full area SEND and AP inspection expected Report 2.6
December 2024: Written Statement of Action closed with 99% of milestones complete Report 2.6, P70
February 2025: First annual progress report approved by Cabinet, with SEND and AP Strategic Improvement Plan launched Report 2.4, 3.1, P70
September 2025: New top up funding banding model and revised SENIF launched Report P16, P52, P58
End of February 2026: SEND reforms White Paper released for consultation until mid-May 2026 Report 2.9, 3.6
9 February 2026: Announcement that the national Safety Valve Programme will close on 1 April 2026 Report 2.9, P90
16 March 2026: Cabinet decision to extend the SEND and AP Programme to end of October 2026
1 April 2026: National Safety Valve Programme closes and Safety Valve payments cease Report 2.9, P70, P90
June 2026: SEND Reform Plan to be written and submitted Report 2.9, 3.6, P70
End of October 2026: Programme work to transition to Business as Usual Report P4
Plain English for the jargon
SEND: Special Educational Needs and Disabilities
AP: Alternative Provision, education for children who cannot attend mainstream school
EHCP: Education, Health and Care Plan, a statutory plan setting out a child or young person's special educational needs and the support they will receive
DSG: Dedicated Schools Grant, the ring-fenced funding for schools provided by the Department for Education
High Needs Block: The element of the DSG that funds SEND provision for children and young people with higher level needs
Safety Valve: A national Department for Education programme that provides additional funding to councils in return for reforms aimed at eliminating DSG High Needs Block deficits
Written Statement of Action (WSoA): An action plan a local authority must produce after a poor inspection, setting out how it will address identified weaknesses
MIP: Mainstream Inclusion Partnership, Hounslow's scheme offering additional funding to mainstream schools to support SEND children without an EHCP
SENIF: SEN Inclusion Funding, a notional payment to early years providers to support inclusive practice
Resource Pathways: Specialist support units within mainstream schools to help children with SEND remain in mainstream education
LEAD: Hounslow's in-house tuition service, Learn Enrich and Develop, supporting children unable to attend traditional schools
LLSE: Lifelong Learning, Skills and Employment Directorate of the London Borough of Hounslow
SENDIASS: Special Educational Needs and Disabilities Information, Advice and Support Service, an independent support service for parents and young people
Local Offer: The council's published information about SEND services, support and provision for children and young people aged 0 to 25
INMSS: Independent Non-Maintained Special Schools, which the council pays to place children with complex needs
NEET: Not in Employment, Education or Training
PCF: Parent Carer Forum, a representative group of parents of children with SEND
BAU: Business as Usual, the council's normal running of services rather than a time-limited project
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
Resolved : · Cabinet noted delivery to date by the programme, since Cabinet approved the Strategic Business Case of the SEND & AP Programme in December 2023. · Cabinet approved the extension of the programme until the end of October 2026 to deliver a thematic approach to inclusion, feeding into development of the SEND Reform Plan June 2026, including use of the remaining £333k of programme budget. Cabinet agreed that the work of the programme will transition to Business as Usual in October 2026.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
1. Note delivery to date by the programme, since Cabinet approved the Strategic Business Case of the SEND & AP Programme in December 2023
2. Approve extension of the programme until the end of October 2026 to deliver a thematic approach to inclusion, feeding into development of the SEND Reform Plan June 2026, including use of the remaining £333k of programme budget
3. Agree that the work of the programme will transition to Business as Usual in October 2026
Official 2. Report Summary
2.1This report is the second annual progress report following on from the Special Educational Needs and Disability (SEND) and Alternative Provision (AP) Cabinet report of December 2023 on transformation and investment to deliver change to the SEND and AP Service.
2.2The programme was originally developed as a result of the actions agreed within the Written Statement of Action (WSoA), to address weaknesses identified through the 2022 Ofsted & CQC Inspection. This was in conjunction with the interventions contained within the Safety Valve (SV) agreement with the Department for Education (DfE), due to the accumulating deficit in the High Needs Block. The programme is included within the People Portfolio of the Council’s Delivery Plan.
2.3Cabinet in December 2023 approved the Strategic Business Case for the SEND & AP Programme and associated funding to cover the programme delivery costs and for operational capacity to deliver programme objectives.
2.4The first progress report was approved by Cabinet in February 2025, showing the programme to be on track and within budget, with Safety Valve (SV) on track to achieve the SV agreement projected deficit in the current year and achieve a £0 DSG deficit by the end of the SV agreement.
2.5This report details progress to date and requests approval for the extension of the programme to the end of October 2026. This will continue effective implementation of SEND transformation and stabilise handover into business as usual, to bring about improved outcomes for children and young people with SEND in Hounslow and meet the requirements of regulators. This will take the form of a tighter thematic programme, after a number of the original projects are handed back to business as usual at the end of March 2026.
2.6The projects within the programme have and continue to progress well. This was validated in October 2024, when an Ofsted and Care Quality Commission (CQC) SEND and AP Inspection took place with an improved middle rating. The Written Statement of Action was closed in December 2024 with 99% of milestones complete. All ongoing work was aligned with the development of the SEND & AP Strategic Improvement Plan, a requirement of the Ofsted /CQC inspection, and embedded into business as usual. This is monitored on a 6–9-month basis by the Department for Education (DfE). The next full area SEND & AP inspection will be within approximately three years of the previous inspection.
2.7Key programme outcomes and impact achieved to date:
• Improved information and guidance: for families & professionals through a new Local Offer & SENDIASS websites, and in person monthly SEND Surgeries.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.