AI summaryCabinet approved retender of Learning Disability Supported Living services at £36,252,518 over up to 8 years, with a new contract starting 1st May 2027 after the current Certitude deal ends.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedReconfigure and retender Learning Disability Supported Living services
Money£36,252,518 totalOver 5 years plus optional 3 year extension, subject to inflation
What happens nextProcurement commencesInvitation to tender publication scheduled for 9/22/2026
Who it affectsLearning disability residents and current provider70 supported living and respite units, current Certitude contract ends 30th April 2027
What was decided
Cabinet authorised commencement of procurement to reconfigure and retender the Learning Disabilities Supported Living services for a contract period of five years with an option to extend for three years, commencing 1st May 2027.
Cabinet delegated authority to the Director of Commissioning, in consultation with the Lead Member for Adult Social Care, Public Health and Health Integration, to agree the final service configuration and award the contracts within the approved budget.
Why
The current contract with Certitude ends on 30th April 2027 with no further extension possible, so doing nothing would leave the council out of contract and subject to legal challenge. Report P2
Recommissioning is preferred to make best use of the available property portfolio, reduce the risk of contract crisis and escalating need, and support residents to maintain independent living. Report P3
The reconfiguration is expected to help mitigate rising adult social care costs and demand, and reduce the number of vulnerable adults needing high-cost social care or hospital admission. Report P4
What happens next
Provider engagement events are planned for May and June 2026, with consultation underway with service users, stakeholders within the local authority and the West London Trust. Report 12.2
The procurement will run as a three-stage process with the ITT published on 9/22/2026, Stage 1 ITT evaluation on 10/23/2026, and Stage 3 moderation on 12/1/2026. Report P48
Following procurement, separate authority will be sought for leases to be awarded to the successful bidder(s) for council-owned buildings in the portfolio. Report 10.3
The money
£36,252,518 Total contract value over proposed 8 years (5 plus 3 year extension), subject to inflation Report 11.1
£4,531,564 Proposed annual cost for the Learning Disability Supported Living Schemes Report 6.2, P16
22,657,822 Total over 5 years (without 3-year extension), £ thousand column Report P16
36,252,515 Total over 8 years (with 3-year extension), as shown in the financial table Report P16
£238,503 Per annum budget reduction applied to support the Council's budget gap Report 11.1
£638k Learning Disabilities Programme saving approved in the 2026/27 Budget Report over 2026/27 and 2027/28 Report 13.3
£88k Expected saving delivered through the re-procurement of the Supported Living contract Report 13.3
Options considered
Chosen: Recommission the Learning Disability Supported Living Schemes (preferred). Enables best use of available property portfolio, reduces risk of contract crisis, supports independent living, and helps mitigate rising adult social care costs. Report P3, P4
Rejected: Do nothing. Would leave the council out of contract from 30th April 2027, subject to legal challenge, and could put clients at risk. Report P2
Rejected: Insource the Supported Living Service. Specialist training and registration requirements would increase costs, and there is potential negative publicity linked to historical service closures. Report P5, P6, P7
Implications
Financial: Annual budget has been reduced by £238,503 to support the Council's budget gap, and £88k of an approved £638k Learning Disabilities saving is expected to be delivered through this re-procurement. Report 11.1, 13.3
Financial: Budget figures do not reflect inflationary increases over the 8-year period; London Living Wage impact is anticipated and a prudent provision will need to be made at annual budget setting. Report 13.2
Legal: Procurement will be undertaken under the Light Touch regime of the Procurement Act 2023 and the Council's Contract Procurement Rules. Report 7.2
Legal: HB Public Law is auditing the proposed properties and reviewing title documents for Registered Provider properties to confirm they can be used for the procurement. Report 7.3
Equalities: All service users have at least one protected characteristic; an Equalities Impact Assessment has been completed and the new service is not expected to have any negative impact on equality groups. Report 8.1, 8.2
Climate: Providers will be required to set out their environmental sustainability approach and plan to move towards carbon neutrality by 2030. Report 9.1
Risk: Some properties not owned by the council may be withdrawn by landlords, potentially reducing supported living capacity and increasing high-cost placements. Report P10
Risk: New governance under the Procurement Act 2023 could delay procurement, shortening the mobilisation period and potentially requiring higher-cost placements. Report P11
Risk: If council lease prices are set too high, market interest may fall, leading to poorer outcomes for residents with complex needs. Report P12
Staffing: Providers will be expected to promote local recruitment, engage with Work Hounslow, attend local recruitment fairs, and support sustainable travel policies. Report 9.3, 10.1
Who and where
Vulnerable adults with learning disabilities currently using supported living services Report 8.2
Current provider Certitude, whose contract ends on 30th April 2027 Report P2
Residents from ethnic minority backgrounds, those with mental health problems, LGBTQ+ residents, and people with learning, physical or sensory disabilities Report 8.2
Registered Providers (including Notting Hill Housing Trust, Central & Cecil, Chrysalis Housing) supplying properties for the schemes Report 10.2, 10.6
West London Trust stakeholders involved in consultation Report 12.2
Timeline
May and June (2026): Provider engagement events to help shape the final service specification Report 12.2
9/22/2026: Publish ITT (Invitation to Tender) Report P48
10/23/2026: Evaluate Stage 1 ITT Report P48
12/1/2026: Stage 3 moderation Report P48
11/8/2026: Moderate Stage 1 ITT Report P48
11/14/2026: Stage 2 presentations Report P48
11/20/2026: Stage 3 ITT submissions Report P48
30th April 2027: Current contract with Certitude ends Report P2
1st May 2027: New Learning Disability Supported Living contract commences
Plain English for the jargon
ITT: Invitation to Tender, the formal document published to invite suppliers to bid for a contract
Light Touch Regime: A procurement process under the Procurement Act 2023 for certain health, social and other specific services
Better Care Fund: A national programme pooling NHS and local authority funding to integrate health and social care
Registered Provider: A social housing landlord, such as a housing association, registered with the social housing regulator
CORE20+5: An NHS England approach focusing on the most deprived 20% of the population and five key clinical areas of health inequality
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
Resolved : · Cabinet authorised commencement of procurement to reconfigure and retender the Learning Disabilities Supported Living services for a contract period of five years with an option to extend for three years totalling a contract value of £36,252,518 (subject to inflation) commencing 1st May 2027. · Cabinet delegated authority to the Director of Commissioning in consultation with the Lead Member for Adult Social Care, Public Health and Health Integration to: a) Agree the final configuration of services to be procured and b) Take all necessary steps to negotiate, agree the terms of and award the contracts within the approved budget referred to at Recommendation 1.1 above to the successful bidders, including entering any associated necessary contractual and property legal documentation.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report Title Learning Disability Supported Living Procurement
Councillor Lily Bath Member Reporting Portfolio holder for Adult Social Care, Public Health and Health Integration
James Hearn, Senior Joint Commissioning Manager – Contact Details Learning Disabilities and Long-Term Conditions [email protected]
For Consideration By Cabinet
Date to be Considered 16 March 2026
Deadline for call-in 24 March 2026
Implementation Date 25 March 2026 (if not Called In)
Affected Wards (All Wards);
Approved by Martin Waddington – Director of ICP and Commissioning 1. Recommendations
Cabinet is asked to: 1.1 Authorise commencement of procurement to reconfigure and retender the Learning Disabilities Supported Living services for a contract period of five years with an option to extend for three years totalling a contract value of £36,252,518 (subject to inflation) commencing 1st May 2027.
1.2Delegate authority to the Director of Commissioning in consultation with the Lead Member for Adult Social Care, Public Health and Health Integration to: a) Agree the final configuration of services to be procured and b) Take all necessary steps to negotiate, agree the terms of and award the contracts within the approved budget referred to at Recommendation 1.1 above to the successful bidders, including entering any associated necessary contractual and property legal documentation.
2. Report Summary
2.1The requirement for care and support falls within the Council’s duty to provide and deliver a robust, good quality care provision as set out in the Care Act 2014. This requires the Council to meet the identified needs of vulnerable people. The supported living services included within the report support the Council’s approach to meeting these needs.
2.2Supported living is an important factor in enabling residents with a learning disability and/or autistic people to live full and rewarding lives, whilst promoting and maximising a resident’s independence in the community. It provides care and support in a fixed location where the resident has a tenancy. Often the accommodation is shared with other residents who also require support.
2.3The Joint Commissioning team, propose to carry out a competitive procurement process with the new contract in place for 1st May 2027. The budget is £4,531,564 per annum with a total eight-year budget of £36,252,518 over the proposed contract term of five years with the option to extend by three years. The contract will include a break clause so that we can give notice should circumstances change.
2.4The services included within the contract provide a range of care and support to some of the boroughs most vulnerable residents, enabling them to live in the community and supporting them to be as independent as possible. The key benefits of commissioning them together include:
• Making best use of the available property portfolio to provide a consistently higher quality offer of support for residents with a learning disability and/or autistic people.
• An improved and more coherent pathway for residents, reducing risk of crisis and escalating need, preventing the need for more costly services such as residential care. • Cost avoidance from preventing higher need, higher cost placements and supporting more vulnerable adults to maintain independence and where possible, step down from higher need placements into lower cost ones.
• Reduced duplication and increased synergy of procurement processes for the provider market by procuring multiple services under the Learning Disabilities Supported Living portfolio.
2.5The key financial benefits are cost avoidance reducing the demand for higher cost placements and an 5% savings target attached through the procurement (as outlined in the budget reports).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.