AI summaryCabinet approves retendering of care, support and catering services for four extra care housing schemes, with eight year budgets of £38,520,445 and £2.4 million.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedCare, support and catering to be retendered
Money£38,520,445 and £2.4 millionBoth over eight years
What happens nextProcurement to beginDirector to award contracts
Who it affectsFour extra care schemesResidents and providers affected
What was decided
Cabinet approved the procurement of care and support services for four extra care housing schemes, with an eight year budget of £38,520,445 over a five year contract with an option to extend by three years.
Cabinet approved the procurement of the catering service for one extra care scheme, with an eight year budget of £2.4 million over a five year contract with an option to extend by three years.
Cabinet delegated authority to the Director of ICP and Commissioning, in consultation with the Lead Member for Adult Social Care, Public Health and Health Integration, to agree the final service configuration and award the contracts within the approved budget.
Why
The supporting documents include a rationale for the budget and recommended options, and an equalities impact assessment. Report 15.1, 15.2
What happens next
The Director of ICP and Commissioning will agree the final configuration of services in line with the council's Contract Procedure Rules.
The Director will negotiate, agree the terms of, and award the contracts to successful bidders, and enter any associated legal documentation, within the approved budget envelope.
The money
£38,520,445 Care and support services for four extra care housing schemes over eight years
£2.4 million Catering service for one extra care scheme over eight years
Implications
Financial: The care contract has an eight year budget of £38,520,445, and the catering contract has a separate eight year budget of £2.4 million.
Legal: The Director is authorised to enter into contractual and property legal documentation needed for the awards.
Equalities: An Equalities Impact Assessment has been prepared as part of the decision pack. Report 15.2
Who and where
Residents of the four extra care housing schemes
Current and prospective care, support and catering providers
The council as commissioner
Timeline
2026-03-16: Cabinet decision taken to commence procurement
Five years: Initial contract term, with an option to extend by three years
Eight years: Total period covered by the approved budgets
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
Resolved : Cabinet gave authority to commence procurement for the reconfiguration and retendering of: 1 The care and support services for four extra care housing schemes with a total eight-year budget of £38,520,445 over a contract term of five years with the option to extend by three years. 2 The catering service for one extra care scheme with a total eight-year budget of £2.4 million over a contract term of five years with the option to extend by three years. Cabinet delegated authority to the Director of ICP and Commissioning in consultation with the Lead Member for Adult Social Care, Public Health and Health Integration to: a. Agree the final configuration of services to be procured in accordance with the Contract Procedure Rules; and Take all necessary steps to negotiate, agree the terms of and award the contracts within the approved budget envelope to the successful bidders, including entering into any associated contractual and property legal documentation.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential Y - Exempt or Exempt Information information in Appendix A - LGA 1972 Sch 12A para 3 applies
Cabinet Key Decision Y
Report Title Commissioning of Extra Care
Councillor Lily Bath Portfolio holder for Adult Social Care, Member Reporting Public Health and Health Integration
Mark Blomfield, Senior Joint Commissioning Manager - Contact Details Preventative Services and Supported Housing [email protected]
For Consideration By Cabinet
Date to be Considered 16 March 2026
Deadline for call-in 24 March 2026
Implementation Date 25 March 2026 (if not Called In)
Affected Wards (All Wards);
Approved by Martin Waddington – Director of ICP and Commissioning 1. Recommendations
Cabinet is asked to:
1. Give authority to commence procurement for the reconfiguration and retendering of: i. The care and support services for four extra care housing schemes with a total eight-year budget of £38,520,445 over a contract term of five years with the option to extend by three years. ii. The catering service for one extra care scheme with a total eight-year budget of £2.4 million over a contract term of five years with the option to extend by three years.
2. Delegate authority to the Director of ICP and Commissioning in consultation with the Lead Member for Adult Social Care, Public Health and Health Integration to: a) Agree the final configuration of services to be procured in accordance with the Contract Procedure Rules; and b) Take all necessary steps to negotiate, agree the terms of and award the contracts within the approved budget envelope to the successful bidders, including entering into any associated contractual and property legal documentation.
2. Report Summary
2.1The following extra care contracts are ending over the next two years:
• Park Lodge, Hounslow – care and support contract ends 31st March 2027 • Bridgewater House, Isleworth – care and support contract ends 31st March 2027 • Bristol Court, Feltham o Care and support contract ends 15th September 2027 o Catering contract ends 31st July 2026 • Greenrod Place, Brentford – care and support contract ends 30th September 2026
2.2Hounslow’s four Extra Care Schemes support vulnerable residents with long- term conditions, frailty and/or disabilities to live independently in their own home with care and support on-site. Extra care prevents and delays the need for much more costly residential and nursing care and helps prevent hospital admissions.
2.3The proposal is to recommission:
• The care and support contracts for Park Lodge and Bridgewater House through a competitive procurement process with the new contracts in place for 1st April 2027. o Park Lodge budget is £811,411 per annum, with a total eight-year budget of £6,491,289 over the proposed contract term of five years with the option to extend by three years. o Bridgewater House budget is £743,463 per annum, with a total eight-year budget of £ 5,947,700 over the proposed contract term of five years with the option to extend by three years. • The care and support contract for Bristol Court through a competitive procurement process with the new contract in place for 16th September 2027. The budget for the care contract is £2,472,038 per annum, with a total eight-year budget of £19,776,304 over the proposed contract term of five years with the option to extend by three years. • The catering contract for Bristol Court through a competitive procurement process with the new contracts in place for 1st July 2026. The budget for the catering contract is £300,000 per annum, with a total eight-year budget of £2.4 million over the proposed contract term of five years with the option to extend by three years. • The care and support contract for Greenrod through a direct award with the new contract in place for 1st October 2026. The budget is £788,144 per annum, with a total eight-year budget of £6,305,151 over the proposed contract term of five years with the option to extend by three years.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.