Sustainable Drainage Schemes (SuDS) for the Borough
NotedExecutive3 papers
AI summaryHounslow Cabinet approved the Flood Alleviation Programme Strategic Business Case and the North West Hounslow Stansfield Road SuDS Outline Business Case, with £3 million planned over two years.
Written from the decision and the officer reportPDF Pro
OutcomeNotedStrategic Business Case and North West Hounslow OBC agreed
Money£3 million plannedover next two financial years
What happens nextPractical completion by March 2027OBCs to finish by April or May 2026
Who it affectsBorough residents in flood-risk areasplus Thames Water and landowners
What was decided
Cabinet noted progress on the Flood Alleviation Programme and the delivery of Sustainable Drainage Schemes across the borough.
Cabinet approved the Hounslow Flood Alleviation Programme Strategic Business Case and the North West Hounslow Stansfield Road Outline Business Case.
Cabinet delegated authority to the Executive Director Finance and Resources to approve funded schemes and add them to the capital programme, and to the Executive Director Strategy and Transformation to enter funding agreements and award contracts.
Why
The Council is the Lead Local Flood Authority with statutory duties under the Flood and Water Management Act 2010 to manage local flood risk, supported by powers in the Land Drainage Act 1991 and Highways Act 1980. Report 7.1
Four borough catchments are known to flood or sit upstream of flooding, and SuDS will cut surface water flood risk, improve water quality, and add green space and biodiversity. Report 11.1, 11.2
The programme sits within the Climate Emergency Action Plan, reducing climate-related flood risk and helping counter heatwave impacts through more green space. Report 9.1
What happens next
All schemes aim to reach practical completion by March 2027, with the remaining Outline Business Cases to be completed by April or May 2026.
The programme aims to secure at least 60% external funding, and ongoing maintenance costs must be confirmed before any scheme is approved to proceed. Report 6.1, 13.3
Each project will involve three rounds of engagement with residents and ward councillors: before the OBC, after the OBC, and before construction. Report 12.3
The money
approximately £3 million Flood Alleviation projects over the next two financial years Report 6.1
£538k total projected cost of the North West Hounslow scheme Report 6.3, P37
£286k Environment Agency grant for North West Hounslow Report 6.3
£252k match funding for North West Hounslow from CIL and the Hounslow Green investment fund Report 6.3
£5k per annum estimated additional maintenance cost for North West Hounslow Report 6.2
£214k estimated budget for Windmill Road, Brentford Report P37
£1 Million estimated budget for Isleworth, St John's Gardens Report P37
£1 Million estimated budget for Isleworth, Redlees Park Report P37
Implications
Financial: Programme targets at least 60% external funding, with maintenance costs to be confirmed before any scheme is approved to proceed. Report 6.1, 13.3
Legal: Landowner permissions are being sought and Thames Water adoption agreements will be needed where schemes connect to its drainage network. Report 7.4, 7.5
Equalities: Accessibility for older and disabled people will be considered at design stage, with input from local Equality, Diversity and Inclusion organisations. Report P15
Climate: Programme is within the Climate Emergency Action Plan, adding green space, biodiversity and reduced flood risk. Report 9.1
Risk: Compliance with grant conditions, planning, environmental requirements and landowner consents must be checked scheme by scheme. Report 7.3, 13.2
Staffing: Delivery sits with the Resilience and Flood Risk Management team within Digital, IT and Resilience. Report 12.1
Who and where
Residents in flood-risk areas of the borough Report 11.1
People with mobility challenges, with accessibility built into design Report P12, P15
Landowners of sites where works are proposed Report 7.4, 7.5
Thames Water Utilities Limited, where schemes connect to the drainage network Report 7.4
Ward councillors, engaged at three stages per project Report 12.3
Timeline
April/ May 2026: Aim to complete remaining Outline Business Cases
August 2026: Estimated completion of Kingsley and Alexandra Schools scheme Report P37
October 2026: Estimated completion of North West Hounslow and Windmill Road schemes Report P37
March 2027: Estimated completion of Isleworth St John's Gardens and Redlees Park schemes, and overall programme practical completion Report P37
Plain English for the jargon
SuDS: Sustainable Drainage Schemes, features that manage surface water at source
LLFA: Lead Local Flood Authority, the council's statutory flood management role
OBC: Outline Business Case, a project approval document
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
Resolved : · Cabinet noted the progress of the Flood Alleviation Programme for the Borough including the delivery of Sustainable Drainage Schemes (SuDS). · Cabinet agreed the Hounslow Flood Alleviation Programme Strategic Business Case in Appendix One- Strategic Business Case. · Cabinet agreed the North West Hounslow Stansfield Road Outline Business case in Appendix Two - Outline Business Case. · Cabinet delegated authority to the Executive Director Finance and Resources to approve the implementation of schemes that have secured funding and their addition to the general fund capital programme. Cabinet delegated authority to the Executive Director Strategy and Transformation to enter into funding agreements with third party funders and to procure and award contracts necessary to deliver the schemes.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report Title Sustainable Drainage Schemes (SuDS) for the Borough
Councillor Shantanu Rajawat, Leader of the Council and Portfolio holder for Strategy, Resources and External Member Reporting Affairs Councillor Katherine Dunne, Portfolio Holder for Climate, Environment and Transport.
Implementation Date 25 March 2026 (if not Called In)
Affected Wards (All Wards);
Approved by 1. Recommendations
Cabinet is asked to:
1. Note the progress of the Flood Alleviation Programme for the Borough including the delivery of Sustainable Drainage Schemes (SuDS).
2. Agree the Hounslow Flood Alleviation Programme Strategic Business Case in Appendix One- Strategic Business Case
3. Agree the North West Hounslow Stansfield Road Outline Business case in Appendix Two - Outline Business Case
4. Delegate authority to the Executive Director Finance and Resources to approve the implementation of schemes that have secured funding and their addition to the general fund capital programme.
5. Delegate authority to the Executive Director Strategy and Transformation to enter into funding agreements with third party funders and to procure and award contracts necessary to deliver the schemes.
2. Report Summary
2.1The Hounslow Flood Alleviation Programme aims to address significant surface and fluvial flood risks across the borough, supporting the Council’s strategic objectives of creating a greener, healthier, and safer community. Informed by the 2021 Surface Water Management Plan (SWMP), the programme targets key catchment areas—Northwest Hounslow, Feltham, Chiswick & Grove Park, and Isleworth & Brentford End—where around 2,900 residential and 476 non-residential properties are at risk during a 1-in-100-year storm event.
2.2The programme proposes the use of Sustainable Drainage Systems (SuDS) and other mitigation strategies in both public and private spaces to manage water runoff, enhance biodiversity, and build climate resilience.
2.3Environment Agency funding has already been utilised to conduct initial feasibility and options appraisals in the areas outlined most at risk in the Surface Water Management Plan and viable projects are progressing to design and construction phases.
2.4The programme also seeks to capitalise on diverse additional funding streams, including Environment Agency (EA) Grant-in-Aid, Department for Education (DfE), Transport for London (TfL), Thames Water, and Community Infrastructure Levy (CIL), aiming for a 60%+ external funding contribution.
2.5The initiative also incorporates stakeholder engagement, equalities and climate considerations, and proactive collaboration with internal teams to identify "latch-on" projects. Governance and delivery will be led by Hounslow’s Lead Local Flood Authority (LLFA), ensuring alignment with capital planning and sustainability objectives.
2.6Currently there are 5 schemes being progressed within the current programme, with total projected costs of £2.93 million through to end of financial year 2026/27, these identified schemes are expected to receive approximately £1.79 million in EA grants. The currently progressing schemes are outlined in Appendix 3.
2.7The North West Hounslow Stansfield Road is the first SuDS scheme in this current programme to have the Outline Business Case approved by the Environment Agency and the Business Case for this scheme is in Appendix 2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.