RESOLVED that the Water Remedial Actions Progress Report be noted.
AI summaryWaverley's Landlord Services Advisory Board noted a water safety works progress report, with contractor SMS Environmental on track and Urban Environments preparing to start risk assessments and maintenance.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that the Water Remedial Actions Progress Report be noted.
Waverley Borough Council
Information note to: Landlord Services Advisory Board Date: 26 March 2026 Author: Paul Cleaver
Email: [email protected]
Information for Scrutiny and Comment
1. Purpose The purpose of this report is to give an overview on Water Hygiene safety programme and works. This includes the contractor performance of SMS Environmental Services Ltd (Remedials) and the Water Risk Assessment (WRA) & Planned Preventative Maintenance (PPM) contractor, Urban Environments Limited.
2. Background SMS Environmental Services Ltd (SMS) entered a contract with Waverley on December 18, 2025, to address and resolve all water safety remedial actions until a resolution is achieved. The contract spans 36 months, with an option for a 24-month extension.
Urban Environment Ltd (UE) have also been contacted to confirm that we are intending to offer the WRA and PPM contract to them, which they have provisionally accepted. A pre-contract meeting has been arranged for Thursday 12 March 2026, for Waverley and UE to confirm any additional information and agree a provisional start date with WBC. This meeting will be prior to entering into to a 36-month contract, with a possible extension for a further 24 months.
3. Overview
SMS is continuing to inspect required requested blocks to confirm the work that has been advised to be undertaken is correct. SMS will continue to prioritise WBC works and Bobbie will keep reviewing resources to prioritise WBCs urgent priority needs. SMS have also confirmed that they are still on target to complete all requested sites that need to be inspected within the 6-month agreed timeframe.
Feasibility surveys are also being completed at Moat Lodge, Cranleigh and Community Room, The Pavillion, Haslemere, due to the size of the water systems in the block to improve mitigations to address water safety risks. Works are also being conducted to remove and/or isolate an asbestos tank in Haslemere. Please refer to Annexe One to see the completed full work programme for overdue Remedial actions.
In February 2026, SMS completed 88% (67) were completed. All works assigned to them for PPMs, due to the remaining 8 tasks needing follow on works. Although SMS
Page 1 of 4 attended to 100% of all tasks within target, they were unable to complete them due to the time the works took and were re-booked.
4. Future Objectives
We have reassurance of continuity and dedication as all works and related documents being tracked on the Opuz system by SMS & Waverley, while working toward a clearer agreed timeline together.
As we are now in contractual talks with Urban Environment Ltd we hope to further clarify and reduce timescales for SMS remedial actions, by the additional contractor completing WRA & PPMs, when in contract. Although new actions may also be identified in this partnership working, timescales for outstanding overdue remedial actions are again predicted to be reduced.
We will continue to re-assess and prioritise all actions on a risk-based profile with majority of 258 high actions now having a planned completion “due date” by the end of April 2026.
Page 2 of 4 Annexe One [need table and maybe a graph to show what needs to be done and work completed – to then update each month]
Total Number Total Actions Number of Date of Remaining Very High High Medium Low Completed new Actions Actions 01/02/2026 58 635 0 0 258 345 32 01/03/2026 01/04/2026 01/05/2026 01/06/2026 01/07/2026 01/08/2026 01/09/2026 01/10/2026 01/11/2026 01/12/2026 01/01/2027
Page 3 of 4 Page 4 of 4
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Water Remedial Actions Progress ReportReport | 345 KB | DownloadRead as text |
Follow Landlord Services Advisory Board (Executive Working Group) at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Capital Programme updateRESOLVED that the Capital Programme update be noted. | Noted | Open |
| 30 Jul 2026 | Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... | Noted | Open |
| 30 Jul 2026 | Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. | Noted | Open |
| 30 Jul 2026 | Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. | Noted | Open |
| 30 Jul 2026 | Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.