CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Waverley Borough Council

Water Remedial Actions Progress Report

Noted Executive 1 paper

AI summaryWaverley's Landlord Services Advisory Board noted a water safety works progress report, with contractor SMS Environmental on track and Urban Environments preparing to start risk assessments and maintenance.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedMonthly update on water safety works and contractors
MoneyNot stated
What happens nextHigh actions by April 2026Most of 258 high-priority actions by end of April 2026
Who it affectsCouncil housing blocksIncluding Moat Lodge, Cranleigh and Haslemere

What was decided

The Board noted the Water Remedial Actions Progress Report, an information note giving an overview of the water hygiene safety programme and contractor performance. Report P5

The report covers SMS Environmental Services Ltd, contracted on 18 December 2025 for 36 months to address water safety remedial actions. Report P6

It also covers Urban Environments Ltd, which has provisionally accepted the Water Risk Assessment and Planned Preventative Maintenance contract, with a pre-contract meeting on 12 March 2026. Report P7

Why

The report is provided to keep the Board informed so it can scrutinise the water safety programme and the performance of the two contractors involved. Report P4, P5

SMS is continuing to inspect blocks, prioritise Waverley's urgent works and remain on target to complete inspections within the 6-month agreed timeframe. Report P9

What happens next

SMS will continue inspections and prioritisation within the 6-month timeframe, with all works and documents tracked on the Opuz system. Report P9, P14

Waverley is in contractual talks with Urban Environments Ltd, which is expected to further reduce timescales once that contract is signed. Report P15

The council will continue to re-assess and prioritise actions on a risk basis, with most of the 258 high actions to have a planned completion date by end of April 2026. Report P16

Implications

  • Risk: Water safety risks at council housing blocks are being addressed through remedial works, risk assessments, and removal or isolation of an asbestos tank at Haslemere. Report P10
  • Other: Two contractor relationships are in place or being finalised: SMS Environmental Services Ltd for remedial works and Urban Environments Ltd for Water Risk Assessment and Planned Preventative Maintenance. Report P6, P7

Who and where

  • Residents of council housing blocks where water safety remedial works are being carried out, including Moat Lodge in Cranleigh and the Community Room at The Pavillion in Haslemere Report P10

Timeline

  • 18 December 2025: SMS Environmental Services Ltd entered a 36-month contract with Waverley for water safety remedial works, with a 24-month extension option Report P6
  • February 2026: SMS completed 88% (67) of assigned Planned Preventative Maintenance tasks, with 8 needing follow-on works; 100% of all tasks were attended within target Report P11, P12
  • 12 March 2026: Pre-contract meeting arranged between Waverley and Urban Environments Ltd for the Water Risk Assessment and Planned Preventative Maintenance contract Report P7
  • 26 March 2026: Landlord Services Advisory Board noted the Water Remedial Actions Progress Report Report P2
  • End of April 2026: Majority of 258 high-priority actions planned to have a completion 'due date' Report P16

Plain English for the jargon

  • PPM: Planned Preventative Maintenance
  • WRA: Water Risk Assessment
  • WBC: Waverley Borough Council
  • SMS: SMS Environmental Services Ltd, the contractor for water safety remedial works
  • UE: Urban Environments Limited, the contractor for Water Risk Assessment and Planned Preventative Maintenance
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item119

Resolved

RESOLVED that the Water Remedial Actions Progress Report be noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Landlord Services Advisory Board (Executive Working Group)

Waverley Borough Council

Information note to: Landlord Services Advisory Board Date: 26 March 2026 Author: Paul Cleaver

Email: [email protected]

Information for Scrutiny and Comment

1. Purpose The purpose of this report is to give an overview on Water Hygiene safety programme and works. This includes the contractor performance of SMS Environmental Services Ltd (Remedials) and the Water Risk Assessment (WRA) & Planned Preventative Maintenance (PPM) contractor, Urban Environments Limited.

2. Background SMS Environmental Services Ltd (SMS) entered a contract with Waverley on December 18, 2025, to address and resolve all water safety remedial actions until a resolution is achieved. The contract spans 36 months, with an option for a 24-month extension.

Urban Environment Ltd (UE) have also been contacted to confirm that we are intending to offer the WRA and PPM contract to them, which they have provisionally accepted. A pre-contract meeting has been arranged for Thursday 12 March 2026, for Waverley and UE to confirm any additional information and agree a provisional start date with WBC. This meeting will be prior to entering into to a 36-month contract, with a possible extension for a further 24 months.

3. Overview

SMS is continuing to inspect required requested blocks to confirm the work that has been advised to be undertaken is correct. SMS will continue to prioritise WBC works and Bobbie will keep reviewing resources to prioritise WBCs urgent priority needs. SMS have also confirmed that they are still on target to complete all requested sites that need to be inspected within the 6-month agreed timeframe.

Feasibility surveys are also being completed at Moat Lodge, Cranleigh and Community Room, The Pavillion, Haslemere, due to the size of the water systems in the block to improve mitigations to address water safety risks. Works are also being conducted to remove and/or isolate an asbestos tank in Haslemere. Please refer to Annexe One to see the completed full work programme for overdue Remedial actions.

In February 2026, SMS completed 88% (67) were completed. All works assigned to them for PPMs, due to the remaining 8 tasks needing follow on works. Although SMS

Page 1 of 4 attended to 100% of all tasks within target, they were unable to complete them due to the time the works took and were re-booked.

4. Future Objectives

We have reassurance of continuity and dedication as all works and related documents being tracked on the Opuz system by SMS & Waverley, while working toward a clearer agreed timeline together.

As we are now in contractual talks with Urban Environment Ltd we hope to further clarify and reduce timescales for SMS remedial actions, by the additional contractor completing WRA & PPMs, when in contract. Although new actions may also be identified in this partnership working, timescales for outstanding overdue remedial actions are again predicted to be reduced.

We will continue to re-assess and prioritise all actions on a risk-based profile with majority of 258 high actions now having a planned completion “due date” by the end of April 2026.

Page 2 of 4 Annexe One [need table and maybe a graph to show what needs to be done and work completed – to then update each month]

Total Number Total Actions Number of Date of Remaining Very High High Medium Low Completed new Actions Actions 01/02/2026 58 635 0 0 258 345 32 01/03/2026 01/04/2026 01/05/2026 01/06/2026 01/07/2026 01/08/2026 01/09/2026 01/10/2026 01/11/2026 01/12/2026 01/01/2027

Page 3 of 4 Page 4 of 4

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Water Remedial Actions Progress ReportReport 345 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 11 attended
PR
Councillor Paul RiversChair, present
TD
Terry DaubneyVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AL
Councillor Andrew LaughtonCommittee Member, apologies
JK
Councillor Jacquie KeenCommittee Member, apologies
AM
Councillor Alan MorrisonCommittee Member, apologies
JR
Councillor John RobiniCommittee Member, apologies
RB
Rod BlackmoreCommittee Member, present
RS
Robert StratfordCommittee Member, present
DW
Dave WilliamsObserver, expected
DM
Dave MaddamsObserver, expected

On this subject at Waverley

Search all
  1. Water Remedial Actions Progress ReportThis decision
  2. Water Remedial Actions Progress ReportNoted
  3. Water Remedial Actions Progress ReportNoted
  4. Water Remedial Actions Progress ReportNoted
  5. New Contract for Water Hygiene Remedial WorksApproved

More from Waverley Landlord Services Advisory Board (Executive Working Group)

All decisions
MeetingDecisionOutcome
30 Jul 2026 Capital Programme updateRESOLVED that the Capital Programme update be noted. Noted Open
30 Jul 2026 Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... Noted Open
30 Jul 2026 Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. Noted Open
30 Jul 2026 Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. Noted Open
30 Jul 2026 Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies