Water Remedial Actions Progress Report

Noted Executive 1 paper

AI summaryWaverley's Landlord Services Advisory Board noted a progress report on water safety remedial works. The current contractor SMS continues until 1 July 2026, when Urban Environment Ltd is expected to take on a new 36-month contract.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action required from the board
MoneyNot stated
What happens nextContractor handover on 1 July 2026UE expected to begin a 36-month contract
Who it affectsCouncil housing tenantsEspecially those in independent living schemes

What was decided

The board noted the Water Remedial Action Progress report without directing further action.

Why

SMS Environmental Services Ltd was contracted on 18 December 2025 to address all water safety remedial actions over 36 months, with a 24-month extension option. Report P1

Urban Environment Ltd has been sent contractual terms on 7 April 2026 and is expected to start planned preventative maintenance from 1 July 2026 under a new 36-month contract. Report P2

High non-access rates in March prevented most remediation quotes from being completed, prompting joint action with SMS to lift access rates above 75%. Report P9, P10

What happens next

SMS will continue completing planned preventative maintenance and site inspections through April 2026, including visits to three locations this month. Report P4, P6

From 27 April 2026, a senior independent living scheme is provisionally scheduled to have its water system replaced, projected to take 30 days or less subject to access and quote approval. Report P12

The council and SMS are working on the Opuz system to produce a clearer interactive dashboard for tracking works. Report P8

Options considered

  • Chosen: Note the progress report. Standard monthly reporting item for the board
  • Chosen: Continue with SMS until July 2026. Allows time to mobilise the new contractor UE and confirm risks are resolved or handed over Report P2, P4
  • Chosen: Award new contract to Urban Environment Ltd. 36-month contract with possible 24-month extension, terms sent on 7 April 2026 Report P2

Implications

  • Risk: There are 636 outstanding water remedial actions (289 high risk and 347 medium risk), with no low-risk items overdue. Report P15, P16
  • Staffing: A handover of water safety contracts from SMS to Urban Environment Ltd is being prepared, with the new contractor expected to start on 1 July 2026. Report P2
  • Other: In March, 12 of 139 tasks attended by SMS required follow-on works, with 127 completed on time. Report P4

Who and where

  • Waverley Borough Council housing tenants Report P4, P10
  • Residents of a senior independent living scheme awaiting a full water system change Report P12
  • SMS Environmental Services Ltd (incumbent contractor until July 2026) Report P1, P2
  • Urban Environment Ltd (prospective new contractor from July 2026) Report P2

Timeline

  • 18 December 2025: SMS Environmental Services Ltd contract with Waverley begins for 36 months with a 24-month extension option Report P1
  • March 2026: SMS attended 139 tasks, completing 127 on time; 12 required follow-on works; high non-access rates recorded Report P4, P9
  • April 2026: SMS due on site at three locations and inspecting further sites over the fortnight Report P6
  • 7 April 2026: Urban Environment Ltd sent contractual terms and conditions to sign Report P2
  • 27 April 2026: Senior independent living scheme provisionally scheduled for water system replacement, projected 30 days or less Report P12
  • 1 July 2026: Urban Environment Ltd expected to begin planned preventative maintenance under a new 36-month contract Report P2

Plain English for the jargon

  • PPM: Planned Preventative Maintenance, routine checks and servicing of water systems
  • CWST: Cold Water Storage Tank
  • HWS: Hot Water System
  • TMV: Thermostatic Mixing Valve, controls water temperature
  • WRA: Water Remedial Action
  • Backflow: Backflow protection fitted to water outlets to prevent contamination
  • Dead leg / Dead end: Pipes where water can stagnate
  • Opuz: Contractor portal system used to track works
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item133

Resolved

RESOLVED that the Water Remedial Action Progress report be noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Landlord Services Advisory Board (Executive Working Group)

Background

SMS Environmental Services Ltd (SMS) entered a contract with Waverley on December 18, 2025, to address and resolve all water safety remedial actions until a resolution is achieved. The contract spans 36 months, with an option for a 24-month extension.

Urban Environment Ltd (UE) have now been sent the contractual terms and conditions on the 7 April 2026, for them to sign. We are currently waiting for UE respond back to the council and confirm they can start WRA’s as soon as possible with the PPMs from the 1 July 2026. This contract is a 36-month contract, with a possible extension for a further 24 months.

3. Overview

SMS are continuing to complete WBCs PPMs until the 1 July 2026 as agreed. This is allowing the council to mobilise the new contractor UE and confirm all risks are identified, have been resolved, or to be given as a priority on handover. In March, SMS attended to 139 tasks and 127 were completed on time. The remaining 12 required follow on works.

SMS have confirmed again that they are still on target to complete a review of all requested sites that need to be inspected, within the 6-month agreed timeframe as tabled below. This is reflected in the timeline chart below, that is populated by the booked or arranged works, on the SMS portal system.

Page 1 of 4 SMS have confirmed that they will be on site at three locations this month (April 2026) and will be inspecting as many additional sites as possible over the next fortnight to agree and progress further required works.

4. Future Objectives

WBC are currently working with SMS to use the information being displayed on the Opuz system to be clearer, so an interactive dashboard is visible to be utilised further

SMS have confirmed that in March, a high percentage of non-access was recorded. Due to this, they were unable to complete most of the remediation quotes for approval.

To improve the access rate SMS and WBC have agreed to use all forms of communication to achieve access rates above 75%, so works are to be agreed and moved forward, with minimal variances. Steps are taken to arrange an out of hours contact to make appointments and share images of water accessories and to incorporate the inspections with other safety and/or repair visits. It will be considered that any other additional information such as a Landlord Gas Safety Records are also to be checked to confirm what water accessories in a property if WBC only has limited information. Additionally, a solution for more information to be obtained is for a template questionnaire that is to be completed by Bracknell Forest Out of Hours call centre, can use. They will call on the customers to request for access appointment to be agreed or for them to confirm what water accessories they have in their property with photographic evidence.

It is projected that 25 quotes a month can be completed and sent to WBC providing customers allowing access becomes more frequent.

Page 2 of 4 On the 27 April 2026, it has been provisionally confirmed that a senior independent living scheme will have their water system changed. This is on provision of access and the quote being approved. Once SMS are on site it is projected that it will take 30 days or less to complete, if access is allowed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Water Remedial Actions Progress ReportReport 171 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 11 attended
PR
Councillor Paul RiversChair, present
TD
Terry DaubneyVice Chair, present
JC
Councillor Janet CroweCommittee Member, apologies
AL
Councillor Andrew LaughtonCommittee Member, apologies
JK
Councillor Jacquie KeenCommittee Member, apologies
AM
Councillor Alan MorrisonCommittee Member, apologies
JR
Councillor John RobiniCommittee Member, apologies
RB
Rod BlackmoreCommittee Member, apologies
RS
Robert StratfordCommittee Member, present
DW
Dave WilliamsObserver, expected
DM
Dave MaddamsObserver, expected

On this subject at Waverley

Search all
  1. Water Remedial Actions Progress ReportThis decision
  2. Water Remedial Actions Progress ReportNoted
  3. Water Remedial Actions Progress ReportNoted
  4. Water Remedial Actions Progress ReportNoted
  5. New Contract for Water Hygiene Remedial WorksApproved

More from Waverley Landlord Services Advisory Board (Executive Working Group)

All decisions
MeetingDecisionOutcome
30 Jul 2026 Capital Programme updateRESOLVED that the Capital Programme update be noted. Noted Open
30 Jul 2026 Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... Noted Open
30 Jul 2026 Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. Noted Open
30 Jul 2026 Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. Noted Open
30 Jul 2026 Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. Noted Open