Resolved
RESOLVED that the Water Remedial Action Progress report be noted.
AI summaryWaverley's Landlord Services Advisory Board noted a progress report on water safety remedial works. The current contractor SMS continues until 1 July 2026, when Urban Environment Ltd is expected to take on a new 36-month contract.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that the Water Remedial Action Progress report be noted.
SMS Environmental Services Ltd (SMS) entered a contract with Waverley on December 18, 2025, to address and resolve all water safety remedial actions until a resolution is achieved. The contract spans 36 months, with an option for a 24-month extension.
Urban Environment Ltd (UE) have now been sent the contractual terms and conditions on the 7 April 2026, for them to sign. We are currently waiting for UE respond back to the council and confirm they can start WRA’s as soon as possible with the PPMs from the 1 July 2026. This contract is a 36-month contract, with a possible extension for a further 24 months.
3. Overview
SMS are continuing to complete WBCs PPMs until the 1 July 2026 as agreed. This is allowing the council to mobilise the new contractor UE and confirm all risks are identified, have been resolved, or to be given as a priority on handover. In March, SMS attended to 139 tasks and 127 were completed on time. The remaining 12 required follow on works.
SMS have confirmed again that they are still on target to complete a review of all requested sites that need to be inspected, within the 6-month agreed timeframe as tabled below. This is reflected in the timeline chart below, that is populated by the booked or arranged works, on the SMS portal system.
Page 1 of 4 SMS have confirmed that they will be on site at three locations this month (April 2026) and will be inspecting as many additional sites as possible over the next fortnight to agree and progress further required works.
4. Future Objectives
WBC are currently working with SMS to use the information being displayed on the Opuz system to be clearer, so an interactive dashboard is visible to be utilised further
SMS have confirmed that in March, a high percentage of non-access was recorded. Due to this, they were unable to complete most of the remediation quotes for approval.
To improve the access rate SMS and WBC have agreed to use all forms of communication to achieve access rates above 75%, so works are to be agreed and moved forward, with minimal variances. Steps are taken to arrange an out of hours contact to make appointments and share images of water accessories and to incorporate the inspections with other safety and/or repair visits. It will be considered that any other additional information such as a Landlord Gas Safety Records are also to be checked to confirm what water accessories in a property if WBC only has limited information. Additionally, a solution for more information to be obtained is for a template questionnaire that is to be completed by Bracknell Forest Out of Hours call centre, can use. They will call on the customers to request for access appointment to be agreed or for them to confirm what water accessories they have in their property with photographic evidence.
It is projected that 25 quotes a month can be completed and sent to WBC providing customers allowing access becomes more frequent.
Page 2 of 4 On the 27 April 2026, it has been provisionally confirmed that a senior independent living scheme will have their water system changed. This is on provision of access and the quote being approved. Once SMS are on site it is projected that it will take 30 days or less to complete, if access is allowed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Water Remedial Actions Progress ReportReport | 171 KB | DownloadRead as text |
Follow Landlord Services Advisory Board (Executive Working Group) at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Capital Programme updateRESOLVED that the Capital Programme update be noted. | Noted | Open |
| 30 Jul 2026 | Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... | Noted | Open |
| 30 Jul 2026 | Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. | Noted | Open |
| 30 Jul 2026 | Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. | Noted | Open |
| 30 Jul 2026 | Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.