Award of EVCI GM Contract to install EV chargepoints throughout Bury

Agreed Executive 1 paper

AI summaryBury Council Cabinet has agreed to let Transport for Greater Manchester award a 20 year concession contract for electric vehicle chargepoints to the highest scoring bidder. The programme draws on £16.158m of government LEVI funding and £1.751m of combined CRSTS funding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedHighest scoring bidder gets 20 year EV contract
Money£16.158m and £1.751mLEVI grant for GM plus combined CRSTS from three boroughs
What happens nextContract by end October 2026GM governance approvals and standstill period expected mid Oct 2026
Who it affectsResidents without off street parkingFocus on on street and near home chargepoints in the borough

What was decided

Cabinet agreed that Transport for Greater Manchester can award the contract to the preferred supplier on behalf of Bury Metropolitan Borough Council, alongside the other nine Greater Manchester local authorities. Report P4

The contract is a 20 year bespoke concession covering design, construction, operation and maintenance of chargepoints, procured through a Competitive Flexible Procedure under the Procurement Act 2023. Report P12

Officers from Bury, Manchester, Stockport and Trafford sat on the Tender Evaluation Panel, and no conflicts of interest were identified after the May 2026 local elections. Report P9, P10

Why

A competitive and transparent procurement process was completed in line with the legislative requirements governing local authority procurement. Report P5

The preferred supplier was the highest scoring bidder and offered the best overall value to the Council, after a procurement that was rewound once and re issued in May 2026 to clarify the installation period, grant funding period and feasibility of implementation. Report P5, P14, P15

No alternative procurement routes were considered appropriate because of the contract value and scope, and a competitive tender was required to meet internal procedures and procurement legislation. Report P5

What happens next

GM Governance Approvals for Contract Award are expected by mid October 2026, followed by an eight day standstill period and notification of successful and unsuccessful suppliers. Report P18, P21

TfGM and the GM Authorities will finalise and sign the contract by the end of October 2026, with the Service Provider appointment also by the end of October 2026. Report P21

Bury will need the governance, resourcing and processes to support site approvals, permits, legal agreements and other authority led activities throughout implementation. Report P22, P23

The money

  • £16.158m Awarded to Greater Manchester from the government's LEVI Fund Report P8
  • £1.751m Combined City Region Sustainable Transport Settlement allocation from Bury, Oldham and Rochdale towards the capital fund Report P8

Options considered

  • Chosen: Competitive tendering process under the Procurement Act 2023. Required to meet internal contract procedures and procurement legislation given the contract value and scope Report P5, P12
  • Rejected: Alternative procurement routes. No alternative procurement routes were considered appropriate due to the contract value and scope Report P5

Implications

  • Financial: The cost of the proposal will be contained within the LEVI and CRSTS funding available to the council, with no additional financial implications; the project is fully funded by grant and supplier investment and, as a concession, should bring a revenue income. Report P30, P34
  • Legal: The procurement used the Competitive Flexible Procedure under the Procurement Act 2023; an Authority Agreement will govern the relationship between TfGM and the GM Authorities once the contract is awarded. Report P12, P32
  • Equalities: The programme is expected to have a positive equality impact by improving access to EV charging for residents without off street parking, including in more densely populated or lower income areas; an Equalities Impact Assessment was completed by TfGM. Report P25, P27
  • Climate: The project supports Bury's carbon neutral target and improves local air quality by expanding EV chargepoints and supporting a shift away from petrol and diesel vehicles. Report P24, P28
  • Risk: Risks identified include supplier performance, procurement challenge, accessibility concerns, local objections, delivery delays from external factors and authority led activities, and equality impact; mitigations include robust contract management, KPIs, engagement and the EQIA. Report P29, P30

Who and where

  • Residents without off street parking or with limited access to public chargepoints within a five minute walk Report P7, P25
  • All 10 Greater Manchester local authorities collaborating on the LEVI programme Report P7, P9, P10
  • Shortlisted chargepoint operators and suppliers who took part in the procurement Report P13, P16

Timeline

  • 12 February 2025: Earlier Cabinet paper set out the LEVI background and proposed procurement approach Report P1, P36
  • 16 December 2025: First main tender responses received; procurement later rewound Report P13
  • May 2026: Rewound procurement: clarified and amended Invitation to Tender issued to the existing shortlisted bidders Report P15
  • Following May 2026 local elections: Conflicts of interest and governance route checked with GM Chief Legal Officers; none declared Report P10
  • 29 June 2026: Main tender responses received from the remaining shortlisted bidders Report P16
  • End July 2026: Main tender assessed and GM Briefing Note on the preferred supplier produced Report P21
  • Mid October 2026: GM Governance Approvals for Contract Award and notification of successful and unsuccessful suppliers Report P21
  • End October 2026: Finalise contract, GM Authorities sign contract, and Service Provider appointed Report P21

Plain English for the jargon

  • CPO: Chargepoint operator
  • CRSTS: City Region Sustainable Transport Settlement
  • EVCI: Electric Vehicle Charging Infrastructure
  • LEVI: Local Electric Vehicle Infrastructure
  • OZEV: Office for Zero Emission Vehicles
  • PSQ: Project Specific Questionnaire, the initial shortlisting stage of the procurement
  • TfGM: Transport for Greater Manchester
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.62

Resolved

Decision(s): Cabinet: - Agreed TfGM on behalf of Bury Metropolitan Borough Council can proceed to award the contract to the Preferred Supplier identified within Part B of this report. Reasons for decision(s): - A competitive and transparent procurement process was undertaken in line with all legislative requirements governing local authority procurement. Following evaluation of all submissions against the agreed criteria, the Preferred Supplier identified within Part B of this report emerged as the highest-scoring bidder and Page 214 offered the best overall value to the Council. Their appointment is therefore proposed. Alternative options considered and rejected: - No alternative procurement routes were considered appropriate due to the contract value and scope. A competitive tendering process was required to meet internal contract procedures and all relevant procurement legislation.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

2. This report provides an update following the detailed paper presented to Cabinet in February 2025, which set out the background to the Local Electric Vehicle Infrastructure (“LEVI”) programme and the proposed procurement approach. The procurement process has now been completed in full compliance with legislative requirements.

3. The purpose of this report is to update Cabinet on the outcome of this Local Electric Vehicle Infrastructure (LEVI) procurement process and to seek approval for Bury Metropolitan Borough Council (“the Council”) to allow Transport for Greater Manchester (“TfGM”) to proceed to contract award with the preferred supplier on behalf of itself (along with the other Greater Manchester local authorities).

Recommendation(s)

4. Cabinet is recommended to agree TfGM on behalf of Bury Metropolitan Borough Council can proceed to award the contract to the Preferred Supplier identified within Part B of this report.

Reasons for recommendation(s) 5. A competitive and transparent procurement process was undertaken in line with all legislative requirements governing local authority procurement. Following evaluation of all submissions against the agreed criteria, the Preferred Supplier identified within Part B of this report emerged as the highest-scoring bidder and offered the best overall value to the Council. Their appointment is therefore proposed. Alternative options considered and rejected 6. No alternative procurement routes were considered appropriate due to the contract value and scope. A competitive tendering process was required to meet internal contract procedures and all relevant procurement legislation. _________________________________________________________ Report Author and Contact Details: Name: Chris Horth Position: Unit Manager – Environment Team Department: Corporate Core E-mail: [email protected] ________________________________________________________________ Background

7. The LEVI Project was launched by the Office for Zero Emission Vehicles (OZEV) to deliver a step change in the deployment of local electric vehicle charging infrastructure (EVCI) across England.

8. The LEVI programme objective is to encourage Chargepoint Operators (CPOs) to supply, install, and operate electric vehicle charging infrastructure (EVCI) in areas that are presently not commercially attractive, through the provision of subsidies. OZEV has recommended achieving this by utilising a concession contract. TfGM and all 10 GM Local Authorities are collaborating on this project, to maximise Charge Point Operators investment and reducing the number of tenders these operators would otherwise need to respond to. Electric Vehicle Charging Infrastructure is to be focused on areas lacking off-street parking or public chargepoints within a five-minute walk.

9. GM was awarded £16.158m from the government’s LEVI Fund, and Bury, Oldham and Rochdale have decided to include their City Region Sustainable Transport Settlement (CRSTS) allocation within the LEVI programme, which totals £1.751m (combined) towards the capital fund.

10. TfGM has been developing the contract strategy and tender pack collectively with all ten GM Local Authorities, in line with OZEV’s direction and guidance. Officers from Bury, Manchester, Stockport, and Trafford, represented the GM Authorities on the Tender Evaluation Panel.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of EVCI GM Contract to install EV chargepoints throughout BuryDecisions 387 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
EO
Councillor Eamonn O'BrienChair, present
AA
Councillor Ayesha ArifCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
GM
Councillor Gavin McGillCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, apologies due to council business
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

On this subject at Bury

Search all
  1. Award of EVCI GM Contract to install EV chargepoints throughout BuryThis decision
  2. Award of EVCI GM Contract to install EV chargepoints throughout Bury Part BNoted

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies