Bury Metropolitan Borough Council
Cabinet, Wednesday 9 September 2026 at 6.00pm

Approval of accepting the Department for Transport grant for the development of the 15112 Bury to Bolton Active Travel Corridor Scheme (Spenfold Lane Bridleway) with approval to award the delivery contract

Approved Executive 2 papers

AI summaryBury Cabinet approves acceptance of a £553,000 Department for Transport grant, administered by Walk Wheel Cycle Trust, to deliver the Spenfold Lane Bridleway active travel scheme, with works starting in October 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCouncil to enter Sub-Grant with WWCT and DfT; Legal to seal documents
Money£553,000Fully DfT funded via WWCT, no Council match funding required
What happens nextWorks October 2026 to February 2027All grant claims to be finalised before March 2027
Who it affectsActive travel route users and landownersOff-highway link between Ainsworth Road and Bolton Road, Spenfold Lane area

What was decided

Cabinet approved the Council entering into a Sub-Grant agreement with Walk Wheel Cycle Trust and the Department for Transport to deliver the 15112 Bury to Bolton Active Travel Corridor Scheme. Report P9

Cabinet authorised Legal to finalise and seal all necessary contract documents so the funding can be accessed. Report P10

Why

The Sub-Grant Agreement is needed so the Council can accept and draw down the approved DfT funding for delivering the scheme. Report P12

Delaying the agreement could put project delivery at risk, jeopardise the funding and harm the Council's reputation with the Department for Transport. Report P13

Both phases received DfT business case approval, with high value for money scores above 2, and the scheme ties in with National Cycle Network improvements between Bury and Bolton. Report P7, P17, P19

What happens next

Finalise the Sub-Grant Agreement and contract documents, with Legal sealing them, then start construction in October 2026 and complete by February 2027. Report P8, P10

Hold public engagement following Cabinet approval, including an in-person event advertised through available communication channels, and continue working with affected landowners on access and Japanese Knotweed treatment. Report P21, P22

Ensure the chosen contractor delivers the social value package, monitored monthly using the National TOMs framework, including local employment, school engagement and carbon reduction measures. Report P23

The money

  • £553,000 Total DfT grant administered by Walk Wheel Cycle Trust to cover full delivery of the Spenfold Lane Bridleway scheme, with no Council match funding required. Report P6, P32, P33

Options considered

  • Rejected: Not proceeding with the scheme. Would result in the loss of DfT funding and missed opportunities to improve local active travel infrastructure. Report P15

Implications

  • Financial: The scheme is fully grant funded with no requirement for Council match funding and no impact on the Council's revenue budget, though scope reductions may be applied if costs rise during delivery. Report P33, P36
  • Legal: There are no legal impediments to accepting the funding, provided the decision-maker has the appropriate delegated authority and the agreement is executed under the Council's constitutional and contractual requirements. Report P35
  • Equalities: A full equality impact assessment has been completed and identified wholly positive impacts, improving access and experience of use across a number of protected characteristics. Report P28
  • Climate: The scheme promotes walking and cycling, supports the National Cycle Network and contributes to Bury's target of carbon neutrality by 2038. Report P27, P29
  • Risk: Failure to enter the Sub-Grant in a timely manner could prevent access to approved funding; mitigation is timely approval and execution of the agreement. Report P31, P32
  • Other: The scheme will widen the existing footway, upgrade surfacing, drainage and lighting, and reclassify the route as a bridleway, creating a year-round accessible off-highway link between Bury and Bolton. Report P5, P15, P16

Who and where

  • Residents travelling actively between Bury town centre and Bolton via the Spenfold Lane area, including those unable to use the current route due to its condition Report P4, P5, P16
  • Affected landowners along the route, where access and Japanese Knotweed treatment have been discussed Report P21
  • Local communities, schools, colleges, NEETs and community groups, through the contractor's social value commitments Report P23
  • Users of National Cycle Network 601, as the scheme forms part of the orbital active travel route around Greater Manchester Report P17, P18

Timeline

  • 09 September 2026: Cabinet decision to accept the DfT grant and authorise the contract Report P2
  • Following Cabinet approval: Public engagement event planned at a suitable local space Report P22
  • October 2026: Construction works scheduled to commence Report P8
  • February 2027: Scheme completion scheduled Report P8
  • Prior to March 2027: All grant claims must be finalised to comply with funding conditions Report P8

Plain English for the jargon

  • WWCT: Walk Wheel Cycle Trust
  • DfT: Department for Transport
  • ATE: Active Travel England
  • TfGM: Transport for Greater Manchester
  • AMAT: Active Mode Appraisal Toolkit
  • NCN: National Cycle Network
  • BCR: Benefit to Cost Ratio, used here to indicate value for money
  • NEETs: Young people Not in Education, Employment or Training
  • National TOMs: National Themes, Outcomes and Measures framework used to monitor social value delivery
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.63

Resolved

Decision(s): Cabinet: - Approved Bury Metropolitan Borough Council entering into the SubGrant agreement with Walk Wheel Cycle Trust (Company number 01797726) and subsequently the Department for Transport for the delivery of the 15112 Bury to Bolton Active Travel Corridor Scheme. - Authorised Legal to finalise and seal all the necessary contract documents to access the funding. Reasons for decision(s): - The Sub?Grant Agreement is required to enable the Council to accept and draw down the approved DfT funding for delivery of the schemes. - Failure to enter into the above agreement in a timely manner may jeopardise project delivery, risking funding withdrawal and impacting the Council’s reputation with the Department for Transport. Alternative options considered and rejected: - Not proceeding with the schemes: This option was rejected as it would result in the loss of DfT funding and missed opportunities to improve local active travel infrastructure.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Key

Report to: Cabinet Date: 09 September 2026 Approval for accepting the Department for Transport grant for the Subject: development of the 15112 Bury to Bolton Active Travel Corridor Scheme (Spenfold Lane Bridleway). Report of Cabinet Member for Environment, Climate Change and Operations

Summary 1. This report seeks formal approval to accept a grant supplied by the Department for Transport (“DfT”) and administered by Walk Wheel Cycle Trust (Company number 01797726) (“WWCT”) to deliver the 15112 Bury to Bolton Active Travel Corridor Scheme.

2. The scheme will improve the existing off-highway route between Ainsworth Road and Bolton Road, providing a safe alternative to the A58 corridor. The improvements will close a gap in the borough's off- highway active travel network, improving connections between key residential areas and contribute to the accessible continuity of the off- highway link between Bury town centre and Bolton. Additionally, the scheme ties in with the improvements to the National Cycle Network (NCN) which is a UK wide network of signed paths and routes for walking, wheeling, cycling and exploring the outdoors.

3. The scheme includes widening the existing footway and enhancing the surfacing, drainage and lighting provision, creating a safer, more accessible route that can be used by residents year-round. This enhances the local public realm and provides options for residents who are unable to use the existing route due to its current condition. The scheme is integral to Bury’s local transport strategy by providing residents with accessible opportunities to engage in active travel. This increased participation in active travel contributes positively to improving health and wellbeing of local residents.

4. The total value of the grant to cover the schemes delivery is £553,000. This is fully funded through the grant provided by the DfT and administered by WWCT. The scheme is delineated into two sections: Phase 1 - 16009 Bellway Homes and Phase 2 - 15697 Hardmans Fold. Both phases will be constructed simultaneously as a singular package of work.

5. Both schemes have received business case approval from DfT based on analysis using the Active Mode Appraisal Toolkit (AMAT) alongside information gathered by WWCT Research & Monitoring Unit. Phase 1 achieved a BCR value of 3.04 and Phase 2 a BCR value of 2.83. According to Active Travel England any scheme achieving a score above 2 is considered high value for money. (Active Travel England, 2023)

6. Approval of the Sub-Grant agreement will enable works to commence in October 2026 with completion scheduled for February 2027, ensuring compliance with funding conditions. Due to the source of the funding, there is a stipulation for all claims to be finalised prior to March 2027.

Recommendation(s) 7. Approve Bury Metropolitan Borough Council entering into the Sub- Grant agreement with Walk Wheel Cycle Trust (Company number 01797726) and subsequently the Department for Transport for the delivery of the 15112 Bury to Bolton Active Travel Corridor Scheme.

8. Authorise Legal to finalise and seal all the necessary contract documents to access the funding.

Reasons for recommendation(s)

9. The SubGrant Agreement is required to enable the Council to accept and draw down the approved DfT funding for delivery of the schemes.

10. Failure to enter into the above agreement in a timely manner may jeopardise project delivery, risking funding withdrawal and impacting the Council’s reputation with the Department for Transport.

Alternative options considered and rejected 11. .

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
15112 General Arrangement Drawings (6)Appendix A 655 KB Download
PDF
Approval of accepting the Department for Transport grant for the development of the 15112 Bury to Bolton Active Travel Corridor Scheme (Spenfold Lane Bridleway) with approval to award the delivery contractDecisions 257 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
EO
Councillor Eamonn O'BrienChair, present
AA
Councillor Ayesha ArifCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
GM
Councillor Gavin McGillCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, apologies due to council business
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open