HRA Capital Investment Programme 2026.2027 Major Refurbishment Works - Heating and Hot Water

Approved Executive 1 paper

AI summaryCabinet delegates authority to award two gas boiler replacement contracts for council homes, combined value about £1.8 million.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAuthority to award and seal gas boiler contracts delegated to directors
MoneyAbout £1.8 million including VATCombined contract value, from a £2,015,000 approved HRA budget
What happens nextContracts start autumn 2026Work to run from September or October 2026 to February or March 2027
Who it affectsCouncil tenants in BuryTenants in Council-owned homes across the Borough of Bury

What was decided

Cabinet delegated authority to the Director of Housing to award the Gas Boiler Replacement Programme contracts, and to the Director of Law and Democratic Services, in consultation with the Director of Housing, to finalise and seal them. Report 11.1, 11.2

The contracts follow a direct award process under the Procurement for Housing Framework, with Axis Europe Limited and British Gas Social Housing Limited invited to tender. Report P6, P7, P8

Why

Tender return and evaluation timescales are tight, so delegation avoids the need to return to Cabinet before awarding. Report P16

Property data shows existing gas boilers are approaching renewal, and replacement is needed to meet the Decent Homes Standard and provide thermal comfort for tenants. Report P20

A-rated boilers are expected to lower fuel consumption and bills, and to help meet the Greater Manchester target of all homes at EPC Band C or above by 2030. Report P28, P30

What happens next

Tender evaluation is expected to be completed in the week commencing 24 August 2026, with contracts to start in September or October 2026. Report P12, P14

The Council reserves the right to award all works to a single contractor if tenders do not show good value for money across both contracts. Report P13

Costs will be met from the HRA approved capital programme. Report P33

The money

  • £2,015,000 HRA Capital Works Programme budget for Major Refurbishment Works, Heating and Hot Water, approved 11 February 2026 Report P3
  • approximately £1.8 million, including VAT Anticipated combined value of the two gas boiler replacement contracts Report P12

Options considered

  • Rejected: Do nothing. Boiler replacements are needed to meet legislative requirements on the Decent Homes Standard and to give tenants energy efficient heating and hot water. Report P20
  • Rejected: Deliver the work in-house through Repairs Direct. Repairs Direct lacks the specialist skills and capacity required for the work. Report P20

Implications

  • Legal: Cabinet can delegate the award under the Council's Constitution and Scheme of Delegations, provided the procurement has been conducted lawfully and within approved criteria. Report P33
  • Financial: Contract costs will be met from the HRA approved capital programme, within the £2,015,000 budget already agreed. Report P3, P33
  • Climate: Ideal Logic 30kW condensing boilers have an ErP A-rating and seasonal efficiency of about 93 to 94 percent, but still rely on natural gas and so continue to produce carbon emissions. Report P29, P30
  • Equalities: Initial screening found no material equalities impact at this stage. Report P28
  • Risk: Risk of properties falling below the Decent Homes Standard if works are not done, and a risk of missing the Greater Manchester target of all homes at EPC C or above by 2030; both mitigated by awarding the contracts. Report P32
  • Staffing: The in-house contractor Repairs Direct was considered but rejected because it lacks the specialist skills and capacity for this work. Report P20

Who and where

  • Tenants of Bury Council homes receiving new gas boilers and hot water systems Report P5, P27
  • Council housing stock across the Borough of Bury, with properties split between North Bury and South Bury lots Report P21
  • Repairs Direct, the in-house contractor, which was assessed as lacking capacity for this specialist work Report P20

Timeline

  • 11 February 2026: Cabinet approved the 2026/27 HRA Capital Works Programme and the £2,015,000 budget for Major Refurbishment Works, Heating and Hot Water. Report P3
  • Week commencing 24 August 2026: Evaluation of tenders expected to be completed. Report P12
  • September or October 2026: Contracts anticipated to commence. Report P14, P22
  • February or March 2027: Contracts scheduled to complete. Report P14, P22
  • By 2030: Greater Manchester target for all council homes to reach EPC Band C or above. Report P28, P32

Plain English for the jargon

  • HRA: Housing Revenue Account, the ring-fenced account for income and spending on council housing.
  • DHS: Decent Homes Standard, the national standard for the condition of social housing.
  • EPC: Energy Performance Certificate, a rating of a property's energy efficiency.
  • PfH: Procurement for Housing, a procurement framework used by social landlords.
  • ErP: Energy related Products, the EU product efficiency rating applied to boilers.
  • GMHP: Greater Manchester Housing Partnership, a body of social housing providers in Greater Manchester.
  • NOx: Nitrogen oxides, polluting emissions produced by combustion, which modern boilers are designed to reduce.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.58

Resolved

Decision (s) Cabinet: · Given the tight timescales associated with the return and evaluation of tenders, Cabinet is requested to: o Delegated authority to award the contract(s) for the Gas Boiler Replacement Programme to the Director of Housing. o Delegated authority for the finalisation and sealing of the contract(s) to the Director of Law and Democratic Services, in consultation with the Director of Housing. This delegation will enable the timely award of the contract(s) and support the delivery of the approved 2026/27 HRA Capital Works Programme. Reasons for recommendation(s) Property data indicates that the existing gas boilers are approaching renewal and upgrade. The investment helps to ensure timely replacement and upgrade of heating and hot water provision for our tenants. Whilst helping to ensure DHS standards are met, which includes property state of repair and provision of thermal comfort. Alternative options considered and rejected · Do nothing: The gas boiler replacements are necessary to help achieve legislative requirements around DHS. Also to ensure our tenants have access to energy efficient heating and hot water provision. · Deliver Inhouse: Due to the specialist scope of work within these contracts there is both a lack of suitable skills and capacity for the in-house contractor (Repairs Direct).
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Key

Date: 09 September Report to: Cabinet 2026 HRA Capital Investment Programme 2026.2027 Major Refurbishment Works - Heating and Hot Water Subject: Request to enter contract with Axis Europe Limited and British Gas Social Housing Limited for Gas boiler replacement programme. Report of Cabinet Member for Housing Services

Summary 1. On 11th February 2026 Cabinet approved the Housing Revenue Account (“HRA”) Capital Works Programme for 2026/27 and a budget of £2,015,000 for Major Refurbishment Works - Heating and Hot Water 2. The purpose of the current report is to seek formal approval of the following contract awards for the Gas boiler replacement programme:

Tender Process

3. Housing Services is seeking to award two contracts for boiler replacement works to domestic properties within Bury Council's social housing stock.

4. Tender prices have been sought through the Procurement for Housing (PfH) Framework, with framework contractors invited to express an interest in delivering the works.

5. Expressions of interest received were reviewed against the framework rankings applicable to the relevant lot. These rankings were established by PfH through the framework procurement process and were based on suppliers' responses to quality and commercial evaluation criteria.

6. In accordance with the framework call-off procedure, the highest-ranked contractors who expressed an interest, Axis Europe Limited(Company number 01991637) and British Gas Social Housing Limited (Company number 01026007), were invited to submit priced tenders for the works.

Evaluation

7. As the procurement is being undertaken via a direct award process under the PfH Framework, the evaluation will primarily focus on price. Submitted tender returns will be benchmarked by Procurement for Housing to ensure value for money. Any pricing anomalies identified during the benchmarking process will be clarified with the relevant contractor and resolved before a recommendation is made.

Timescales

8. The evaluation exercise is expected to be completed during the week commencing 24 August 2026. The anticipated combined contract value is approximately £1.8 million, including VAT.

9. Housing Services has made it clear to bidders that Bury Council reserves the right to award all works to a single contractor if the tender submissions do not demonstrate appropriate value for money across both contracts.

10. The contract(s) are anticipated to commence in September/October 2026, with completion scheduled for February/March 2027.

Recommendation (s)

11. Given the tight timescales associated with the return and evaluation of tenders, Cabinet is requested to:

11.1Delegate authority to award the contract(s) for the Gas Boiler Replacement Programme to the Director of Housing.

11.2Delegate authority for the finalisation and sealing of the contract(s) to the Director of Law and Democratic Services, in consultation with the Director of Housing.

12. This delegation will enable the timely award of the contract(s) and support the delivery of the approved 2026/27 HRA Capital Works Programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HRA Capital Investment Programme 2026.2027 Major Refurbishment Works: Heating and Hot WaterDecisions 251 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
EO
Councillor Eamonn O'BrienChair, present
AA
Councillor Ayesha ArifCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
GM
Councillor Gavin McGillCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, apologies due to council business
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

On this subject at Bury

Search all
  1. HRA Capital Investment Programme 2026.2027 Major Refurbishment Works - Heating and Hot WaterThis decision
  2. Contract awards in respect of the HRA Capital Investment Programme 2026/27 and Carbon Reduction - Sustainability Improvement MeasuresApproved
  3. Contract awards in respect of the HRA Capital Investment Programme 2026/27 and Carbon Reduction - Sustainability Improvement MeasuresAgreed
  4. Procurement and approval of contract for the HRA Capital Programme 2024/25Approved
  5. Procurement and approval of various contracts for the HRA Capital Programme 2024/5Approved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open